Earned Value
In the Open Standard
Sonia RoseMember for 17 years 11 months
- Created
- 5
- 1
0
Dear schedulers,
I am trying to re-baseline a schedule that have already progress. I should track the performance of this schedule using EVM, But when assigning this baseline (with progress)and prior to change the Data Date, my SPI is > 1 while logically it must be equal to 1 because the project is on schedule.
Any suggestions?
I am trying to re-baseline a schedule that have already progress. I should track the performance of this schedule using EVM, But when assigning this baseline (with progress)and prior to change the Data Date, my SPI is > 1 while logically it must be equal to 1 because the project is on schedule.
Any suggestions?
5 replies
Oldest firstLog in or join to reply