PRODUCTION RATE FOR BUILDING COOLING TOWERS

Nelson MediloMember for 17 years 11 months
Created
7
30
0
Production Rates for Building Cooling Towers

7 replies

Oldest first
  1. 0
    Nelson Medilo ·
    Hi to all planners!

    Im looking for production rates for building cooling towers such as installation of grid fillings, windscreen, drift eliminators, etc. Some of the activities is the same as civil construction works.

    If someone can share their knowledge please post at this board or email me at use private message service

    Looking forward to your response.

    Thanks! More power!
  2. 0
    Samer Zawaydeh ·
    Dear Nelson,

    Usually production rates are associated with the workers skill, evironmental factors, and site difficulty.

    And the best people to provide you with the production rates are the contruction supervisors that you have at site. Being with their estimates and then modify your numbers to according to the actual progress at site.

    With kind regards,

    Samer
  3. 0
    Nelson Medilo ·
    Hi Samer,

    Thank you for your response. I will do it as per your advise and talk to my supervisors.

    Anyway, maybe you might have some production rates that i can be referred from, preferably in metric system, can you share me a copy?

    Thank you and more power.

    regards,

    nelson
  4. 0
    Daniel Limson ·
    Nelson,

    There are two phases, the civil/structural phase and the cooling tower assembly usually done by the vendors or suppliers themselves.

    The first phase depends on where the cooling tower is located or sitting, normally they are mounted on the roof of the building, while others have a special structure built for the cooling tower itself.

    The 2nd phase involves assembly and piping connections of the cooling tower. Of course, the cooling tower assembly will depend on the number of cooling towers, normally one (1) cooling tower can be assembled in 4-5 weeks provided all the materials have been shipped at the same time.

    Best regards,
    Daniel
  5. 0
    Mai Tawfeq ·
    Let me advice u dear:

    The most important in cooling tower programme is providing essential mile stones since such kind of products needs a lot of authorities approvals, and in regard of the productivity rate, u can apply same rate of other similar works wither MEP or Finishing.

    thanks
  6. 0
    Nelson Medilo ·
    hi to all,

    good day.

    thank you for all the information and really appreciated.

    Mai,

    Do you have productivity rates that i can use in this programme, would you mind to share?

    Thanks in advance..
  7. 0
    Mai Tawfeq ·
    can u list what exactly looking for