Dear Members

I need urgent advice on conversion procedures for conversion of my programme in MSP 2007 to Primavera P7.

I have tried many ways but failed to do successfull conversion.
 

Please advice what is the correct procedures to convert MSP 2007 to P7  

2 replies

Oldest first
  1. 0
    Ishmael Mutsvanemoto ·

    Conversion from MSP2007 to P7

    1. Import as an MPX/MPP.

    2. Note and delete all headers that have been converted to activity descriptions - you notice them by the fact that theactivity typr becomes 'WBS Summary'

    3. Change all other activities type from 'Resource Dependent' to 'Task Dependent' if you so wish

    4. Check the calenders, links, constraints.

    5. Schedule

    NB: Ensure the activie MS Project is closed before you import.

     

    Give me a shout if you get stuck - +447985252112

     

    Regards

     

    Ishmael

  2. 0
    David Young ·

    Vineet  Simple way is to save

    Vineet 

     

    Simple way is to save MSP file as XML . You will find this Option when  you Click File->Save As .XML.

    You can also do import setting in Primavera to get MSP data like Text 1 , Text 2 and other.

    Untile Next Time 

    David Young 

    http://myprimavera.co.uk

    david.young@myprimavera.co.uk

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?