can i have some example on road and infrastructure sequential activity program in primavera as an example

Thank you.

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·

    Dear Rahel, The major

    Dear Rahel,

    The major activities in most projects are

    Shop Drawings and Approval

    Material Submittals and Approval

    Procurement

    Construction

    Testing and Commissioning and Handing Over.

    You can get the first three sections and the last section from the BOQs and the Issued for Construction Drawings. On the other hand, the Construction depends on the construction team.

    For a Road Construction project, I assume that you need to site with your construction team and divide the project into zones and work on them according to priority. Once you have done that the activities generally are:

    1. Site Survey.

    2. Cut and fill

    3. Civil Works according to the cross section of the road that you have; layer 1, 2, 3, etc. You will need to notive the MEP work included inside the civil works and sequence it accordingly.

    4. Isolate the concrete structures (box culverts, bridges, etc) and have them in a separte category.

    5. You might have side walks, paint, signals, etc after the end of construction. You will have to reveiw the BOQ and Plan them accordingly.

    I hope that the information helps a little. If you be more specific and describe the project more, we can assist more.

    With kind regards,

    Samer

  2. 0
    Mike Testro ·

    Hi Raheel Primavera is noit

    Hi Raheel

    Primavera is noit the best software for linear projects - you should be considering Tilos or Vicos.

    Best regards

     

    Mike Testro

  3. 0
    Ashraf Alawady ·

    Dear All, the main activities

    Dear All,

    the main activities for the raods ad infrastructure are cotaining but ot limited to the followig

    prjoject commencemet date

    Mobilisation

    settig out and survey works

    obtaiig costructio NOCs from all concerned authortities

    trial trenches and varification of the existing services(utiliyies) location

    protectio or relocation of existig utilities - as required

    layig of ew utilities

    submit shop drawings for road works

    approval of shop drwings

    submit the subcotractors for approval

    approval of subcontractors

    sumit materials submittals for approval

    approva materials submittals

    procurement of the matirals

    earth works (cut and fill)

    prepare the formatio layer

    layig of subbase layer

    layig of road base layer

    spray betuminous prim coat

    laying of ashpalt base course

    spary tack coat

    layig of asphalt weraring course

    roads marking

    errectig traffic sigs

    general site cleaning and prepare the project for handingover

    hand over the project.