Deletion of Provisional Sum ITem and giving it to another contractor
In the Open Standard
Umer MehmoodMember for 18 years 3 months
- Created
- 3
- 2
0
Dear Friends
i am working in UAE on a construction project , our contract is lump sump project . There are some items in the BOQ under the heading of provisional sum , there are simple concrete jobs whose rate can be taken from main BOQ , however the client is not agreeing on these rates and delete this item( building) from provisional sum and given to some other contractor
Please can some one advice as per UAE Law they have the right for this
your advice will be very helpful to me
Thanks
Best Regards
Umer Mehmood
Planning Manager
050-3115397
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?