E.O.T approval
- Created
- 1
- 1
Hi all
Actually, we are working on FIDIC YELLOW contract, the contract period was over since 30/06/2011 and we submitted an EOT till 20/010/2012, untill now, the client didnt response to our EOT and my GM refuse to do any work at site untill we have approval on EOT.
90% of work is over, but the client refuse to issue a TOC to us and he is currently use our product. T&C is done and inspected by the engineer.
For issuing a TOC, we need to submit a final account, can i apply for final account while the project in some area not yet finished ?
also, what about the unsetteled VOPs, can i show it in the final account ?
Please advice
1 reply