Skip to content

WBS Questions

Richard FeynmanMember for 15 years 2 months
Created
17
63
0

Hello, I am new to the study of project management and am working on implementing a WBS. IF I understand it correctly, here is one example of phase breakdown for a project:

1. Define
2. Plan
3. Execute
4. Close Out

Questions:
A. I assume that somewhere in #2 the WBS is created?

B. Does the WBS then get listed primarily under #3? In other words, if I were creating a project outline and listing WBS tasks under phases  would it be:
Execute
-WBS Task 1...and so on?

C. So let's use construction as an example, and this gets top the heart of my question. Every example construction WBS that I see starts with the assumption that the home is already designed, for instance it will start with "excavate" or something like that. But *where* does all of the design work fall that has to take place before that, for instance, the drafting of the architectural plans? How can the scope be worth the paper it is written on if there is no design? Isn't the design integral to creating a meaningful WBS, not to mention an estimate? OR is the design something that gets carried out in the execution phase, as on the other hand it does seems to fall under part of the project "work"??

Hopefully my question makes sense as I may be working under some false understandings.

Thank you in advance for any assistance.

17 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Richard You seem to be

    Hi Richard

    You seem to be missing the point of a WBS system.

    It is simply a set of codes that allow estimating and accounting systems link up with programming tasks.

    You do not have to have a WBS to create a construction programme - I never use them at all.

    If you have design elements in your programme then they are best bolted on the construction programme.

    Best regards

    Mike Testro

  2. 0
    Richard Feynman ·

    Thanks Mike.  This question

    Thanks Mike.  This question may indicate that I'm still missing the point, but I'll ask it anyway :-)!  Let's remove the WBS from the equation altogether.  Let's say we have a construction project for building a 100,000 sq ft building.  We'll call it "build new office center". 

    1. How can we perform phases 1 & 2 (define; plan) if we don't even have a design (no architectural prints) yet?  That's why I asked if having the architect perform the design would be considered part of the "define" phase?

    2. OR, would we have two projects, with the first being project named "design new office center".  And then after that project is completed, initiate a new project named "build office center"?  In that case it would make sense to me that for the first project define and plan could be performed in a meaningful way, because they'd be preparing to perform the design.  Where I'm getting confused is if "build new office center" is one project that includes the design and the build, than I don't see how you can adequately define and plan for the project when you don't even have blueprints.

    Thanks again.

  3. 0
    Richard Feynman ·

    Sorry, I have no idea why my

    Sorry, I have no idea why my last reply is showing up 3 times.  And I don't see a delete option.  Nor do I see why it's showing up above Mike's post instead of below it.  Not used to this forum.

  4. 0
    Gary Whitehead ·

    Mukltiple posts deleted -this

    Mukltiple posts deleted -this often happens when you hit the "save" button more than once while waiting for the next page to load.

    With reference to your query:

    1. Some design would happen in the 'define' phase (eg concept design -how many buildings? iconic ultra-modern architectural wet-dream, or something more mundane?). Some design would happen in the 'plan' phase (eg construction materials and methodologies). Some may not happen until the 'excecute' phase (eg external lighting layouts)

    2. Whether design & construction would be part of a single project or seperate ones would depend on who is doing them. In a Design and Build contract arrangement where a single organisatino does both, you could reasonably expect there to a be a single project including both design and build.

     

    I think where you're getting confused is with your original premise of these 4 phases. I have never seen a project schedule, wbs, estimate, contract, scope doc, or anything split down like this. a more common (and I would suggest useful) split would be something like design, procurement, construction, and commissioning.

     

     

    Cheers,

     

    G

  5. 0
    Mike Testro ·

    Hi Richard If you have not

    Hi Richard

    If you have not got any form of design then you cannot programme the construction.

    Your query would take place at Level 1 Programme where the feasibility study is taking place.

    You have to use your experience to block out level 2 bar durations for the several stages of the project implementation.

    I once created a bill of quantities and a level 4 construction programme on the basis of an estate agents brochure for a Central London office block - so you don't need much detail to start work.

    My own experience told me that a piled basement would be necessary to accomodate the number of parking spaces and the plant rooms - and what external cladding would be allowed by the fire regulations etc.

    Best regards

    Mike Testro

  6. 0
    Richard Feynman ·

    Thank you both for your

    Thank you both for your replies.

  7. 0
    Richard Feynman ·

    Edit: Post deleted, Gary, I

    Edit: Post deleted, Gary, I reread your response, and it now makes sense to me.

  8. 0
    Richard Feynman ·

    "Whether design &

    "Whether design & construction would be part of a single project or seperate ones would depend on who is doing them. In a Design and Build contract arrangement where a single organisatino does both, you could reasonably expect there to a be a single project including both design and build."

    While I realize there is no "right" or "wrong" on this issue, I'd like to hear more input on it from members.  Let's assume that the same firm is doing the design and the build.  How would you decide on whether the design and build should be defined as a single project, or two distinct projects?  What questions should I ask myself?  I realize of course that this is a very broad question and if you need more detail I can supply it.  If it helps, "design" would usually consist of 160 - 320 man-hours.  Build would be several times that.  Also, in our business design and build are typically seperate in terms of agreements and payments.  That is, first we perform a design based on an agreement and get paid for it.  As part of the design deliverable we provide an estimate for build.  If the design and estimate are accepted (they virtually always are), then a contract is signed and a desposit obtained for build.

    Personally, I'm leaning towards seperating it into two projects because it seems as though it would quite nicely categorize and drive focus on the two major elements of each of our projects, and I like the idea of not exerting a single ounce of focus on build as part of the project management until the design phase is done.  But whether this is a good idea, or I'm just leaning towards it because it's easier for me to conceptualize, I don't know. 

    I should note that in my own instance I am not talking about construction, but rather than bore everyone with the unncessary details, let's just say that the construction field is an excellent metaphor for my field.  Good project management is rarely employed or even followed in my field, and I'm working to change that for my own business.

  9. 0
    Mike Testro ·

    Hi Richard The design and

    Hi Richard

    The design and construction are integrated phases of the same project and should not be separated.

    It doesn't matter if the design is in house or procured by the employer.

    The problem is that you have to prepare the construction programme before the detailed design sequence can be linked in.

    The usual sequence is:

    Outline design prepared

    BOQ - cost plan

    Construction programme at level 4

    A lot of members in PP state that they cannot prepare a level 4 programme from an outline design but it can be done if you know what you are building.

    The detailed design can then be integrated with the construction programme.

    All this is explained in the training modules to be found at

    www.planningacademy.org

    Best regards

    Mike Testro 

  10. 0
    Gary Whitehead ·

    Questions you should be

    Questions you should be asking yourself would include:

     

    1. Is it true to say that the entire design “project” must be completed before any work on the construction “project” can begin?  Or is it a bit more complex than that? (It generally is) If the latter, that would lean you towards a single project so you could accurately reflect these more complex logical links between design and construction activities
    2. Will your companies internal systems (accounting, legal, timesheets, QA, etc) be treating these two elements as a single project or two? There are clear benefits to synergising your approach with the rest of the business.
    3. Will both design & construction elements be utilising some of the same resources (e.g. project management, planning, etc)? Could limitations on resource availability drive delay? Does your planning software allow you to easily report on resource utilisation across multiple projects?
    4. Do the two elements form part of a single contract, or are they separate? If separate, are they both with the same client? Do they both have similar contractual requirements in terms of planning? Contractually, what would be the position if delays to, or failures with, an element of the design work caused a delay to contract completion for construction?
  11. 0
    Richard Feynman ·

    Mike and Gary,Thanks again

    Mike and Gary,

    Thanks again for sharing your expertise, it is invaluable to me at this stage and both of your answers help a lot.

    BTW, part of my earlier misunderstanding was that I was under the impression that define/plan/execute/close were "top level" sequential phases that would be at the top of the WBS and that other phases (procure/build) would fall underneath those in a sequential outline view.  Therefore my mind kept asking "how can I plan if I don't even have a design yet".  A little more reading has made me understand (I think) that define/plan etc. are not merely sequential phases but are considered "process groups" which can be applied to different phases throughout the lifecycle of a project.  Correct?

  12. 0
    Richard Feynman ·

    BTW, your answers helped give

    BTW, your answers helped give me a clear answer - while seperating design and built into two projects were intitially attractive to me from a conceptual point of view, ONE project is the best answer for us.

  13. 0
    Donald Harrold ·

    One of the problems that I

    One of the problems that I perennially see is projects being carried out without proper functional integration between the engineering, procurement, construction and commissioning disciplines.  It is essential that the WBS is created in such a way the clear links can be established between functions, phases and deliverables.  Only by doing this can a clear understanding of the program constraints and drivers, either internal or external, be established.  I think that construction planning at level 4 without a mature well developed design and reliable procurement plan is largely a waste of time.  Inevitably the schedule will have to be revised when the engineering and procurement details have been established.         

  14. 0
    Mike Testro ·

    Hi Donald I agree with what

    Hi Donald

    I agree with what you say but how is this acheived by using WBS?

    Best regards

    Mike Testro

  15. 0
    Anoon Iimos ·

    Mike,You might try, vertical

    Mike,

    You might try, vertical WBS, and horizontal WBS. Vertical being discipline wise (Standard); and horizontal as control areas (variables).

     

    cheers

  16. 0
    Mike Testro ·

    Hi Anoon One of the benefits

    Hi Anoon

    One of the benefits of using powerproject software is that WBS is optional - that is why I have never had to use it.

    Best regards

    Mike Testro

  17. 0
    Anoon Iimos ·

    Mike,I cannot imagine on how

    Mike,

    I cannot imagine on how you do your planning without having to use WBS. I believe the definition of WBS is work breakdown structure.

    So in vertical and horizontal structuring you may need codings so as to reflect your timeline which is always horizontal (I supposed).

     

    cheers

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?