How to import a project with budgeted man hours

Carlos OchoaMember for 15 years 2 months
Created
3
25
0

I have been trying to import a project in P6.  The project has budgeted man hours, but when i finish the import the hours are all changed.  What is the correct way of doing it?

3 replies

Oldest first
  1. 0
    Arun Vasanth ·

    Friends Please Answer the

    Friends

    Please Answer the above Question???

    Regards

    Arun

  2. 0
    Noe Radovan ·

    Check if your time period,

    Check if your time period, calendar settings, time units and also resources calendar of your P6. is matching on the imported file  If you want to match the budgeted hours check all your settings.  It could be the imported file is using hours as time unit but your program is days or vice versa. Possible also is your calendar used has the same name as your P6 but different workweek and timeperiods.

  3. 0
    Zoltan Palffy ·

    add a column for duration

    add a column for duration type and change all of your duration types to fixed duration and units/time 

    the run a global change 

    go to tools global change 

    Then New

    make sure the top part of the global change where it says Select Subject Area change it to Activity Resource Assignment

    make the global change look like this 

    where

    resource ID Name is not equal to (leave the next part blank)

    then 

    Calculate cost from units = No 

    then on the right select Change 

    then on the botom committ