Skip to content

Construction methodology for excavation & pilling on a hilly Terrain

Sankar VijayanMember for 16 years 1 month
Created
7
60
0

Dear All,

I require your valuable suggestion for this topic

We are going to construct a high rise building on a hilly Terrain.The Risk associated with the  project is high.The excavation & pilling  has to be done on a hilly area (with steep slope).For structural stability the structural consultant choose pile foundation even though the soil is hard strata .Approximate depth of excavation is 25 m & Pile dia varies from 600 -1200.What type of piling to be done .Can any rig stand on this steep terrain.What are the risks to be mitigated.How the excavation to be done there is a chance of land slides.

 

Regards

Sankar

7 replies

Oldest first
  1. 0
    J Karthik Kumer ·

    Dear sankar vijayan,  i am

    Dear sankar vijayan,

     i am karthik from chennai, could u explan what is manhour for excavation, pcc, rcc, backfilling other civil works,

    1unit excavation = (manhour) how many manhour

    like that above mentioned all, pls explain

     

    j.karthik

    nscl

    use private message service

  2. 0
    Mike Testro ·

    Hi Sankar With the

    Hi Sankar

    With the possibility of landslides you must either use a battered deep excavation beyond the natural angle of repose of the soil - this depends on the size of your site.

    Or you can use a series of retaining wall to hold back the excavated surface to create a level piling platform.

    Always start from the bottom and work upwards.

    The retaining walls could be steel sheet piling with earth anchors and walings or conctete using secant piling.

    I would suggest secant piling as the same rig can be used for this and the structural piles.

    Remember that a secant pile is not structurally sound until it has its insitu ring beam constructed and cured.

    If the thin white line on your drawing is the natural gound level then at the level of the 3rd flight of stair there is a relatively flat profile which can be made level by cut and fill.

    From this you can drive the lower level piles over to the end of the lift shaft using bilnd boring to reach the level of top of the structure support piles and cantilevered retaining piles up to the next two levels. - Stair 5.

    Using backfill you now create your second platform and re do the same process up to stair 9.

    When you have all your piles in place you can start the excavation to the formation profile within the retaining walls breaking out the temporary suppourt piles as you go.

    All of this has to be designed by a qualified structural engineer.

    The planning problems are quite tricky especially as you have to allow for curing times of the ring beams and vertical haul roads for the rig access.

    Best regards

    Mike Testro

  3. 0
    Sankar Vijayan ·

    Dear Sir,Thank you Very much

    Dear Sir,

    Thank you Very much for your Valuable Suggestions .As a fresher in this field this information is very much useful to me.I am discussing the scenario & methodology you mentioned with our Planning deparment.Hoping your assistance & attention always.

    Thanks & Regards

    Sankar

  4. 0
    Mike Testro ·

    Hi Sankar Two other methods

    Hi Sankar

    Two other methods are worth considering.

    1.  Temporary piling platforms formed by braced scaffolding falsework.

    2.  Excavated battered slope stabilisation using pinned reinforced sprayed grout.

    Don't forget - always get the design and methods checked by a qualified strucrural engineer before chosing the best method.

    Best regards

    Mike testro

  5. 0
    Sankar Vijayan ·

    Dear sir,The main Problem

    Dear sir,

    The main Problem with this project is Logistics .How the rig reach there .What type of rig iis it?One way is prepare haul road .You have any experiance in such project.And also you mentioned that as we go up demolish temperory pile (whether it is secant pile).In this case secent pile act a permanent retention system and also can you please give some brief explanation regarding Temperory Pile Platform formed by braced scaffolding work

    Regards

    Sankar

  6. 0
    Mike Testro ·

    Hi Sankar My reference to

    Hi Sankar

    My reference to demolishing secant piling was for the temporary cantilevered piles that are holding up the higher platforms.

    The haul road would have to be a hairpin traverse across the slope - no mean feat of engineering in itself.

    Consider the option of cutting back to the batter and the bottom formation and stabilising the slopes with pinned back reinforced grout.

    It is best to use an earthfill piling platform if at all possible but if the loose end cannot be restrained by natural repose or support piling then a space frame platform may be the best option.

    You really need the input from a qualified strucrural engineer so I suggest you take this problem in that direction.

    Best regards

    Mike Testro

  7. 0
    Sankar Vijayan ·

    Thank you sir for your

    Thank you sir for your valuable suggestions.We will have detailed meeting with our structural engineers soon so that i can put forward all these methods .Regarding the other project risks especially while tendering ,can you share some of thse risks (to be considered while costing)so that we shouldnt end up with loss after quoting such risky projects

    Thanks & Regards

    Sankar Vijayan

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?