additional work

Ronron MartinezMember for 16 years 10 months
Created
2
1
0

Hi ALL,

Need your advise, as per the contract quantity there are some work scope not in the contract quantity and the client want to do without any variation order. please advise.

Regard

Ron

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ronron A change in

    Hi Ronron

    A change in quantities is not an automatic variation to the contract.

    Check your contract conditions to ascertain what you have contracted to do and who holds the quantity risk.

    Best regards

    Mike Testro

  2. 0
    Ronron Martinez ·

    Hi Mike Many thanks for your

    Hi Mike

     

    Many thanks for your reply, actually is not the quantity increase. There is additional work scope not in our contract?

    Regards

    Ron