Forecasting and Trending
In the Open Standard
Scott ParkerMember for 14 years 2 months
- Created
- 2
- 4
0
I currently am running projects that are fairly short in duration (3 months). I progress daily and progress using Physical % Complete since I can measure units completed. Since the duration of each project is short my CPI seems to be manic. Up one week then down the next. I was wondering if anyone can suggest a strategy to forecast and trend these types of project better. Much appreciated.