Dear All

In the tender document drawing few items only mention however in the Issue for construction drawing have mention few items but not indicated in the scope of works under the contract clause, Is it a variation order, please advise.

Regards,

Ronron
 

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Ronron It all depends on

    Hi Ronron

    It all depends on the type of contract.

    If you have a remeasurable BOQ then you get paid for the work you do the number of drawings is variable as the work progresses.

    Anything else - such as fixed price - EPC - then you have a big problem without a clearly defined scopeof work.

    Best regards

    Mike Testro