Skip to content

Multiple NEC contracts one project

Matt HuntMember for 16 years 8 months
Created
1
3
0
If an early warning/compensation event delays contractor A to the extent that it will delay contractor B is contractor B entitled to a compensation event. If contractor b has not started on site I assume he can not claim an extension to his contract and hence additional costs as his whole contract period has moved as a block

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Matt Contractor B would be

    Hi Matt

    Contractor B would be entitled to an extension of time - shifting the work period to a later date is an EoT.

    But then if Contractor A had both contracts then delays on one contract would entitle Contractor A to an EoT on the other.

    This is true even if the first delay was not a compensation event.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?