Multiple NEC contracts one project
In the Open Standard
Matt HuntMember for 16 years 8 months
- Created
- 1
- 3
0
If an early warning/compensation event delays contractor A to the extent that it will delay contractor B is contractor B entitled to a compensation event. If contractor b has not started on site I assume he can not claim an extension to his contract and hence additional costs as his whole contract period has moved as a block