Status of Finish Date
In the Open Standard
Tanveer Ahmad NiaziMember for 20 years 10 months
- Created
- 2
- 4
0
Dear All
1- Once the Contractor has submitted an Interim EoT Claim
2- The Engineer has accepted that to review
3- Responds to the contractor that the claim is being reviewed
The contractual / revised finish date is considered withhold / null & void (can no more be considered as Contractual).
Is the above statement right? Either case please provide some reference and evidence if possible
Cheers - Tanveer