How to generate S-curve for physical progress where work consist of different units

Anil MahapatraMember for 15 years 1 month
Created
4
3
0

Dear Sir/Mam

Am working in a sewerage project, I want to generate a S-curve for physical Progress

Problem I am facing for S-curve:

We have different unit of work, like Sewer line, pipe laying and house sewer connection in meter, manhole chambers, and inspection chambers and pump stations in numbers. And WBS of my construction schedule is based on the areas (divide based on different areas of the city)

By using MS project or Oracle Primavera is it possible to generate a physical progress curve which represents the entire project. If yes kindly help.

I heard that bucket planning can solve it. But I don’t have any idea what is that and how it work. If you can light me on that

Kindly advice also if is there a better way to structure my construction schedule.

Kindly help.

Thank you

Anil mahapatra

4 replies

Oldest first
  1. 0
    Jerome Odeh ·

    Hi Anil,You should be able to

    Hi Anil,

    You should be able to generate s-curve for the entire project but you'll need a common unit of measurement for the different work scopes.

    Have you considered using cost as your common denominator? Your different work scopes will have cost estimates that you can use.

     

    =jerome

  2. 0
    Daniel Limson ·

    Hi Jerome,In addition to

    Hi Jerome,

    In addition to cost, You can use Manhours or Mandays or weighted value for each element of work.

     

    Regards,

    Daniel

  3. 0
    Anil Mahapatra ·

    Hi Mr. jeromeThank you for

    Hi Mr. jerome

    Thank you for your valuable input.

    However there is probelm in cost. The proejct is done by different contractors and we are a PMC by the client.

    So thay don't give any information about cost in schedule. only the monthly billing schedule.

    So Is there any other way we can do may be using actual work.

    thank you

    Anil

  4. 0
    Jerome Odeh ·

    Hi Anil,I understand your

    Hi Anil,

    I understand your problem.

    Use weighted value of each work package as suggested by Daniel. You can get the weighted values from the client.

    You should get something like this, so that the weightings total to 100%. 

    S#Work PackageWeighted Value (%)
    1Sewer Line20%
    2Lay Pipe45%
    3Sewer Connection5%
    4Manhole Chambers10%
    5Chamber Inspections10%
    6Pump Stations10%
     Total100%

     With this, you should be able to set-up s-curve for physical progress measurement. I'm assuming you have your physical progress rules of credit (progress metrics) already defined.

    =jerome

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?