Skip to content

Omission

Ronron MartinezMember for 16 years 10 months
Created
3
2
0

Dear All,

Would like to clarify the omission of the scope of work in the contract BQ, material has been procure and the work has been carried out however in the middle of the project schedule the client cancelled the design for the particular work and omit in the contract BQ and doesn't allowed to claim to material purchase and halfway work done, any advise please.

Regards

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RonronI need a bit of

    Hi Ronron

    I need a bit of clarification.

    Was the work actually installed before the omission?

    Best regards

    Mike Testro

  2. 0
    Ronron Martinez ·

    Dear Mike,Thank for the

    Dear Mike,

    Thank for the reply,

    THe omission of work was the underground piping it was cancelled by client. however we had procure the material and install few die-inch. anyway to claim this omission of work.

    Regards

  3. 0
    Mike Testro ·

    Hi RonronYou should claim for

    Hi Ronron

    You should claim for the work and materials procured prior to the cancellation.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?