Progress Tracking for MEP Progects
- Created
- 1
- 1
Dear All,
I started working as a Planning Engineer from Aug-2015. Till today I'm facing problems in tracking the work progress from site. Whenever I request for site progress updates I'm not getting any proper updates. The site people says that its the Planning engineer’s duty to go to site and track the project. My management is also not taking any initiative to solve the problem. The project is >100Million AED with LV, ELV, HVAC, P&D, Fire Forgetting in the scope. The total building area of 81,900+ Sq. M.
So I want to know whether it is the Planning Engineer's duty to do this. I was thinking that the Site Engineers are responsible for giving me the updates. I'm really confused and can't manage my work because all my work is relied upon the updates from site.
The other project that I'm handling also has Project value >100 Million AED, but from there I'm getting weekly updates in proper manner even if I'm not dedicated to there. (Please note the this project consist of all Typical buildings and it is easy for tracking).
Please advise on how to tackle this issue. I'm willing to go to site and take updates as necessary but it will clash with all the reports that I've to submit to Main Contractor on Weekly Basis (There are like a dozen reports to be submitted) and I've to chase all people from the store keeper, supervisors to engineers and construction managers for the updates.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?