NEC3 CE and programme ahead of schedule
In the Open Standard
Jonathan RobertsMember for 10 years 4 months
- Created
- 0
- 6
0
Hi,
We have a contract where there is an accepted programme which shows the planned completion and a completion date. Due to a compensation event no 1 the planned completion and completion date has been extended by 2 days.
Due to good weather progress has been ahead of schedule on site but now another CE has raised which will effect the critical path.
As the planned completion is now 2 days ahead of schedule, ie what it was prior to CE 1, is the contractor entitled to claim the 2 days delay costs (preliminaries) that has already been implemented in CE1. In effect claiming the same 2 days twice?
If this is the case does the completion date move out by a further 2 days as well?
Many thanks
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?