Skip to content

Earned Value - Man Hours

Jithin KambhikanamMember for 15 years 6 months
Created
9
3
0

Hello Everyone Can EArned Value be caluclated for Manhours and Then can we forecast the expected manhours to complete. I made a table to put those thing to get a forecasted manhours which is based on Productivity which is same as CPI. Please comment and let me know your ideas to make it better,

I have put an example by putting Project Managers to Claculate the Forecast at completion.

And please do let us know if there are other ways too.

 If the above one is not Clear as it is from Excel here is the cut and paste but without the shades below,

   C = A X B  F = D X E  J = A X HK = J / DL = N - DM = L X EN = A / KP = N X EQ = J - DR = A - N
DisciplineBudget Actual G - Planned % H - Actual %J - Earned Man-hoursK - ProductivityForecasted Forecasted Total Variance 
A - Man-hoursB - Unit Rate C - Total CostD - Man-hoursE - Unit Rate F - Total CostL - Man-hoursM - CostN - Man-hoursP - CostQ - Till to dateR - Overall
Project Manager100660018610820.0%15.0%15.000.83102 120 -3.00-20

Regards

Jithin 

9 replies

Oldest first
  1. 0
    Rafael Davila ·

    Hello Everyone Can Earned

    Hello Everyone Can Earned Value be calculated for Manhours.

    • Yes.

    and Then can we forecast the expected manhours to complete.

    • Yes but you will need software capable of modeling resource production rate and its relation to activity duration and resource assignments in order to get a dynamic projection, otherwise much manual adjustments might be needed.
    • Keep in mind EVM is an overly simplified model that might miss the impact of changes in resource production rates among different activities each having a different impact on critical path. 
    • Mh EVM photo MH EVM_zpsvnmg4anu.jpg
  2. 0
    Jithin Kambhikanam ·

    Hi Rafael,Thanks I got your

    Hi Rafael,

    Thanks I got your point but I was thinking of making something by doing a productivity analysis and putting it in excel to Forecast like by following up these values,

    • EV = Budgeted Man - hours X Actual % Achieved
    • Productivity = EV/Actual Man - hours used for doing the Actual % Achieved
    • Forecasted Man - hours = Budgeted Man- hours / Productivity

    Wouldn't this give us a Forecast Man - hours.

     

    Regards

    Jithin

  3. 0
    Jithin Kambhikanam ·

    Thanks Rafael again.Ya I do

    Thanks Rafael again.

    Ya I do know about Construction but I was looking for Engineering. For one of the Project we are doing the engineering so inorder to forecast the engineering manhours should we use the Productivity ( the Multiplying Formula which I had put down) or check with each dicipline engineers of how much would they take to complete the remaining work. 

    So it is related to Engineering so there is no Volume or Work.

     

    Thanks

    Jithin

  4. 0
    Rafael Davila ·

    If an activity can be done in

    If an activity can be done in 40 hours using 5 resources A and I assign a volume of work of 100 % then the productivity would be 100%/[40hoursx4resource] =  100/[40x4] %/resource-hr = .625 %/resource-hr

    For the average resource I would assign a productivity of  .625 %/resource-h

    For a lower production resource I would assign a productivity of .80x.625 = .500 %/resource-h, if a rookie then perhaps even a lower production rate shall be considered.

    The following example can give you an idea of what I would do.

     photo Arbitrary VOW_zpsw6fhq3zn.jpg

    Of course this is a very simple scenario, more interesting is when you want some resources to produce a fixed amount of the volume of work, say in Activity 3 Resources A instead of 45.45 let it be 70.00 and Resources B the remaining 30.00. 

     photo VOW00x2_zpscbhqkkyr.jpg

    The calculations are easier and dynamic if integral within the CPM.  Also much needed transparency is provided in this way.  Insane doing this using manual methods if similar to the prior shifts example, but with thousands of activities shifting in time as soon as there is some progress. 

    Whenever you want to change any parameter just change it and click the mouse, so easy.

  5. 0
    Rafael Davila ·

    For Productivity type

    For Productivity type activities we use Volumes of Work, their duration is calculated during scheduling. 

    > Budgeted Cost of Work Performed (BCWP), or Earned Value is budgeted cost of actually performed activity works. BCWP is also the value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component.  EV = Budget x %work done.

    > Productivity or Production Rate = [volume of work] / [effort hours]; productivity or production rate is a parameter that can change as things happen different to as planned, predicted production rate can be different to current at different periods, can be different for different shifts and different teams working on the same activity.  This can complicate the calculations for activity durations if your software does not relate production rate and volume of work to activity duration.

    > For volume of work we use units everyone at the job-site understand and uses such as CM [cubic meters] of rock excavation, EA [each] bricks, SF [square foot] of tile installation. Earned Value is calclulated for similar units.

    > Forecasted Man - hours = [actual man-hours] + [remaining volume of work] / [adjusted productivity];  in case of different shifts the calculations for activity duration can be very tricky.

    SVOW001 photo ShiftsVOW_zpsgk6fe1wp.jpg

    I use Best of Breed approach, we collect data using our financial system, we use the CPM for forecasting purposes.

    • http://www.aronsonllc.com/sites/default/files/2014%20S300CRE%20Variance%20Analysis.pdf 
  6. 0
    Rafael Davila ·

    Duration type activities do

    Duration type activities do not have volume of work associated so % done is a % of elapsed time, an example of such activity in my industry is concrete curing.  

    For activities where there is some work related to it but cannot be easily measured in pure deterministic way maybe there is no better option than to assign an arbitrary volume of 100 and make an educated guess of % done.  Even for these type of activities different resources have different production rates and somehow it shall be defined.  Perhaps most Engineering activities fall in this category.

    In my case perhaps 98% of Construction activities have a clear volume of work associated, while a 1% are pure duration type and a 1% are very difficult to measure.  For such activities I use volume of work activity type, with an arbitrary value of 100 and volume of work unit %.  This allows me to define resource/team/shifts production rates for such activities.

    I am aware of how difficult it can be to measure activity progress on some jobs, Engineering, IT and Development jobs in particular.  But still you have to deal with the issue on having different resources/teams/shifts with different productivity. 

  7. 0
    Jithin Kambhikanam ·

    So I guess the formula which

    So I guess the formula which I use should be OK as it is not related to Quantity or Duration. AS you said some item which are not quantitative in construction can be measured by duration - like Curing.

    But here the case is not related to Duration or Quantity. Here it is a Document (Deliuverable) - Example Foundation Detail, Load List etc...

    I guess I can caluclate it by the Productivity of that Dicipline,

    Say for MEchanical Dicipline for 5 deliverable the Budgeted hour was,

    Budgeted Hours = 50

    Actual No of deliverable Completed = 2

    Actual Hours = 25

    Planned Hours = 20

    Productivity = 0.8

    Forecasted Overall Hours =50 (Budgeted Hours) /0.8(Productivity) = 62.5 Hours

    If the Productivity was 1 = the Forecasted hours would be 50 Itself.

     

    Regards

    Jithin

  8. 0
    Rafael Davila ·

    About - If the Productivity

    About - If the Productivity was 1 = the Forecasted hours would be 50 Itself.  

    • If planned and actual productivity whatever value it is are equal then the forecast would be as planned itself,  the rest to me is kind of convoluted for me.

    Deliveries are always related to some quantity, either measured as time or as a volume of work or as a lump-sum the whole measured as either 1 LS or 100%.  

    • I do not understand how can you talk about productivity when there is nothing against which to measure it. Duration is a quantity, volume of work is a quantity. 
    • Source DataPlanned Actual % of planned amount
      man hours50mh25mh50.00%
      quantity5ea2ea/mh40.00%
      Productivity0.1ea/mh0.08ea/mh80.00%
    • % of planned amount is unitless but it is based on some reference amount/quantity.
    • The usual practice to quantify deliverables when there is no simple measure is to use 1 LS as the quantity and unit, it is very simple.  The measure of productivity when using LS is relative to the specific deliverable and cannot be directly applied to other deliverables, it is better to use other physical measures when possible. You could say for certain Concrete Pouring activity we have Concrete = 1 LS or you might say we have Concrete = 80 CM, the latter is a better approach. 
  9. 0
    Jithin Kambhikanam ·

    So how would you Forecast the

    So how would you Forecast the extra manhours for Engineering.

    We know the " No of Deliverables in that Engineering"  and How much manhours are allocated to do each deliverable.

    One forecast can be done by asking each Dicipline Engineers- of how much more manhours are required to complete the remaining deliverable or Use the Productivity of Each Dicipline to calculate the Forecast.

    Please dont think about Construction or Procurement. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?