Hi,
Tracking Progress for plans without resources
The schedule should be Updated (progressed) on a regular basis and progress recorded at that point. The date on which progress is reported is known by a number of different terms such as Data Date, Update Date, Time Now and Status Date. The Current Data Date is the field Primavera uses to record this date. The Data Date is NOT the date that the report is printed but rather the date that reflects when the update information was gathered.
Whatever the frequency chosen for updating, you will have to collect the following activity information in order to update a schedule:
• Completed activities
-Actual Start date
-Actual Finish dates
• In-progress activities
-Actual Start date
- Percentage Completed
-Duration or Expected Finish Date of the Activity
• Un-started work
-Any revisions to activities that have not started
- New activities representing scope changes
-Revisions to logic that represent changes to the plan
The schedule may be updated after this information has been collected. The recorded progress is compared to the Baseline dates