Project Control Tolerance

Moutaz AldeibMember for 22 years 9 months
Created
3
3
0

Hi All,

how can i define the project control tolerance criteria for schedule, cost and quality? what is the base?

best,

moutaz

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you can define and set that

    you can define and set that threshold in terms of float. ie the schedule falls behind schedule by -20 days then a revised schedule will be requested. If the forecasted cost above the budgted amount by X % then a red flag goes up. If the number of deficencies  reaches a certain % then a red flag goes up and investigation begins as to what the root cause for the deficiencies is and recommendation on how to correct it. 

  2. 0
    Moutaz Aldeib ·

    thanks Zoltan, my question

    thanks Zoltan, my question is: Is there a specific rule depends on the size of the project?

    best,

    muataz

  3. 0
    Zoltan Palffy ·

    for float it does not depened

    for float it does not depened on a project size 

    for cost it does not depened on size

    fro quality it does depend on size and you would have to nornmalize the deficencies basd on the size of the project 