Hi,

Is a negative schedule variance indicates that the project will not finish on time?

In my opinion NO. because, as of the reporting period, critical items planned values may be achieved and keeping the completion date on time. meantime few non critical activities may not be started on time, keeping the EV less than the PV.

So negative variance only indicates that the value of work done is not as much as of planned.

Share your opinion

Best Regards

Kannan

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    negative float yes ngeative

    negative float yes 

    ngeative variance no because there can be float in the schedule that tyou are comparing against. 

  2. 0
    Kannan CP ·

    agreed and thanks

    agreed and thanks Zoltan..

    Regards

    Kannan

  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 

  4. 0
    Patrick Weaver ·

    If you are not doing enough

    If you are not doing enough work there will eventually be a major issue -ve SV highlight this.

    If you are not doing the right work there is a problem -ve Float highlights this. 

    You need both sets of information (and their trends) to really understand the situation on a project. See: https://mosaicprojects.com.au/Resources_Papers_117.html

  5. 0
    Praveen Malik ·

    Hi Kannan, You are right.

    Hi Kannan, You are right. Negative SV only means that project is behind, as per the current schedule, on status or control date. It does not give any indication of the future work. For more on variances, you can look at https://www.pmbypm.com/basics-earned-value-analysis/

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?