how boq and Drawing assist contractor in formulation of tender?

2 replies

Oldest first
  1. 0
    Patrick Weaver ·

    1.  BOQ = Bill of

    1.  BOQ = Bill of Quantities.  This is a listing of all of the materials and works to be accomplished as part of the contract.  BoQ is a very 'English' concept, derived from the old 'Standard Method of Measurement (SMM7) for more up to date information see: https://www.designingbuildings.co.uk/wiki/Standard_Method_of_Measurement_SMM7

    2. Drawings tell you what needs to be built (ie, the design you are required to tender against and build if successful). 

    3. Formulating the estimate is then a very skilled activity, for some ideas see: https://mosaicprojects.com.au/WhitePapers/WP1051_Cost_Estimating.pdf

  2. 0
    Muhammad Ahmad ·

    Thank brother

    Thank brother

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?