Project % of completion

Ahmad ObeidatMember for 7 years 6 months
Created
1
3
0

Good day,

how I can calculate the % complete of the project when I have the quantities increased from the baseline ???

if I want to consider the actual completed work for some items and it almost reached the baseline or BOQ quantity, this will give a wrong indication of the project % complete.

which numbers I should consider??

regards,

1 reply

Oldest first
  1. 0
    Santosh Bhat ·

    The Revised Forecast at

    The Revised Forecast at Completion.