Project % of completion
In the Open Standard
Ahmad ObeidatMember for 7 years 6 months
- Created
- 1
- 3
0
Good day,
how I can calculate the % complete of the project when I have the quantities increased from the baseline ???
if I want to consider the actual completed work for some items and it almost reached the baseline or BOQ quantity, this will give a wrong indication of the project % complete.
which numbers I should consider??
regards,
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?