not possible to get a clear definition of client needs?

Eampm PmjhaMember for 7 years 3 months
Created
3
3
0

Hello guys, can anyone anser this question please? Thank a lot

 

Traditional project management (TPM) depends heavily on being able to clearly define what the client needs. You cannot create a detailed project plan without that information. Within the framework of the TPM, what could you do if it were not possible to get a clear definition of client needs?

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Follow the drawings and

    Follow the drawings and specification.

  2. 0
    Stephen Devaux ·

    1. Make assumptions re

    1. Make assumptions re requirements.

    2. Document them.

    3. Distribute them to sponsor/customer with a "fused" date when scope will be frozen and changing it will require ECP/ECO.

    4. Continue planning WBS/schedule/resources/budget/fee based on assumptions.

    5. Change WBS/schedule/resources/budget/fee per feedback from sponsor/customer.

    6. Freeze scope.

    7. Complete plan.

     

    Projects involving contracts will also require negotiating/finalizing the contract.

     

    Fraternally in project management,

    Steve the Bajan

     

    P.S. Congrats to you and England, Mike! (Of course, ya couldn'ta done it without a Bajan bowling the super over!)

  3. 0
    Zoltan Palffy ·

    agree with Stephen

    agree with Stephen