Hi All Planners,

ewcwntly i appeared  in a job interview for the position of planning Engineer. The interviewer was the MD of the company and had a good knowldge of primavera. I am shareing these question (and the answers) to all my planet fellows. I dont know all of them were right or not. If any senior & experienced planner is there, please comment if the answer was wrong. Thanx

4-what is reate reflection?

A- it makes a copy of our project plan in our project port folio with the option to merge all or selected changes to the main program.

5- P3 can not show cost?

A- it is absolutely wrong, P3 has cost management and can shoe 100% of the B.O.Q.

6- How?

A- by asigning the cost to all the (labor, nolabor & material) resorces accordingly using cost accounts catagoriy. or simply asign one resource "C = Cost" or "V = Valve" to all the activities through the cost account directory.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?