Baseline / target discussion
In the Open Standard
Stephen Fawcett-JonesMember for 21 years 3 months
- Created
- 5
- 3
0
Can anyone help on our discussion with our client. We are currently 5 weeks into a shutdown and due to various reasons are behind with the schedule. The client has asked to re-baseline the plan. We are at 35% complete with approximately 4 weeks to go, we have said that we will re-target ("re-baseline") the schedule to meet the original end date. He is insisting on the S Curve being taken back to 0% and to start from the new agreed re-baseline date. This is where we differ we think it should remain at 35% and progress from there. Are we missing the point ?
Cheers
Steve
Cheers
Steve