Dear Planners,

I’m involved with pipeline and umbilical jobs which we’ve around 7 platfroms there and 6 barges for transportation.

According to the above mentioned pls advise me which one is better for our wtg consumption...either of budgett cost(barges rental) or budgett quantity (manhours)?????

1 reply

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Hi Izam,

    Use both!

    The cost will be use for top level management to see

    While manhours will be use for lower level (supervision).

    Cheers,

    Charlie