Hi,
Is there any other way to produce a P10, P50, and P90 dates besides using Pertmaster?

I’m handing a couple of projects that is still on the conceptual stage and i’ve been told that it will be difficult to identify the risk factors at this stage which are key elements for the risk analysis process in Pertmaster.

Cheers,
Daniel T. S

1 reply

Oldest first
  1. 0
    Andrew Donlan ·
    @risk add on for MSP