LNG regasification Terminal Pre-Comm/Comm

Romano MennaMember for 21 years 1 month
Created
1
2
0
I need to assess the feasibility of construction timing, for a LNG regasification on-shore Terminal facility, based on pre-coom and commissioning sequence and timing: does anybody have experience to help me?
It is my first LNG project and it has process flows different from most of my past experiences (power, rail, petro-chem, etc.).
Thank you.

Romano

1 reply

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Romano,

    These are usually highly specialized project. You will need as a planner to identify the complete deliverable. Subsequently, you can ask you team members to assign the activities, sequence, and the durations.

    You will need the input from all the people involved in the project; Engineering, Procurement, HR to determine available resource, Construction teams, Quality Control teams, shipping and handling team, and financial people to ensure cash flow to support all the above activities.

    Good luck,

    Samer