Quick Risk Template - distributions

Dennis HanksMember for 19 years 6 months
Created
3
6
0
Is there any way to change the default distribution in the quick risk template for Pertmaster 8.53?

Current default distributions are BetaPert, Enhanced, Triangle, and Uniform. I would like to add Trigen and make it the default.

Software no longer maintained by client, so stuck at 8.53 and no longer have access to Primavera support.

Any thoughts appreciated. Thanks.

3 replies

Oldest first
  1. 0
    Andrew Podolny ·
    Hi Dennis.
    There is workaround - add 2 columns into your Risk View:
    1st from Risk Inputs group - Duration Distribution
    2nd from Risk Inputs group - Use Duration Distribution

    Assign the Trigen distribution to the topmost activity through the bottom panel - you’ll see the changes in the recently added columns. Use ’Fill Down’ feature to fill these 2 columns.

    Regards,
    Andrew
  2. 0
    Dennis Hanks ·
    Thanks Andrew;

    This is what I currently do - part of my standard view. I was hoping to eliminate the fill down step by making the default change in Quick Risk.
  3. 0
    Sudheerkumar Gurram ·

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?