Risks move the schedule?

Adam GarnhamMember for 15 years
Created
2
3
0

I am looking to put risks into P6 and wondered if these have any effect on the schedule? Our aim is to use the risks section of P6 as an area to record all project risks but dont want these to have any effect on the schedule. Is this possible?

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    Monte Carlo will run based on

    Monte Carlo will run based on the time distribution for each activity you specify, not on the deterministic durations. Your P6 deterministic schedule shall not be affected by the MC runs.

    In the end risks will drive how things happen and what you will record on your updates. Theoretically if you eliminate extraneous risk, which is impossible, if you execute the job thousand times you will get thousand different outcomes that will have the same distribution Monte Carlo display. Remember it is just a model.

  2. 0
    Dennis Hanks ·

    Adam;You are building a

    Adam;

    You are building a rudimentary Risk Register, it will have no impact on the schedule by itself.  Later if you decide to apply the data in the register through 'what-ifs', then you may see change, but it will not be a direct result of identifying any risk(s).

     

    BTW: You can export the P6 Risk Register to help bild a more useful register in PRA via the Tools link.  Not sure if there is any other way to re-use the data deveoped in P6.