Negative Schedule Variance with positive cost variance

Shafeek K AMember for 10 years 5 months
Created
1
6
0

Hi,

I understand that having a negative schedule variance with a positive cost variance is a rare case scenario. Could you please cite me a practical situation where this could be possible ?

 

Thanks.

1 reply

Oldest first
  1. 0
    Vladimir Liberzon ·

    When works were done slower

    When works were done slower than expected but actual expenses are lower than planned.

    Why did you place your post in the risk forum?