Resource leveling in PRA
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 8 months
- Created
- 4
- 1
0
Hello planners,
Where could I find some comprehensive documentation about the nudge and resource leveling process in Primavera Risk Analysis?
Having tried to level the same project in P6, MS Project, Spider and finally PRA, I find that PRA does not reschedule the project the same way as the 3 others.
Thank you
4 replies