Project Scheduler - Uploading of Actuals Costs into PS8

Calvin RajuMember for 7 years 2 months
Created
4
6
0

Hi all,

We have just migrated to SAP Business By Design, and I am struggling to download Actuals Labour sts and Material/Expense Costs into PS8. Im currently doing this manually by hand, and its not a small task, trust me.

We used to do this in the old ERP system via an MS Access database, but now Im struggling.

Any ideas how I can download Prject Costs, per task from an EXL file?

Thank you kindly.

Calvin

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Calvin,could you emphasize

    Hi Calvin,

    could you emphasize ? what is an EXL file?

    as far as I can remember (I do not have PS8 on my PC), it is possible to import any kind of data in a PS8 project file from an XLS, CSV or MDB file

    as a fervent user of PS5/6/7/8, I would be pleased to give you a hand if possible.

    Alexandre

  2. 0
    Calvin Raju ·

    Hi Alexandre. My

    Hi Alexandre. My apologies.typing on my mobile is hard..i tend to get the spellings incorrect. I meant to say XML type. Like you..i love PS8...ive just managed to input 6months of ACWP into PS8...a huge task...and i want to do this as a monthly task...can you help me please? If you share your email address i will send you my XML file that i wish to input..i would like to preferable import into PS8 instead to manually typing in data..an mdb would be perfect for this application...Many thanks
  3. 0
    Calvin Raju ·

    Hi Alexandre. My

    Hi Alexandre. My apologies.typing on my mobile is hard..i tend to get the spellings incorrect. I meant to say XML type. Like you..i love PS8...ive just managed to input 6months of ACWP into PS8...a huge task...and i want to do this as a monthly task...can you help me please? If you share your email address i will send you my XML file that i wish to input..i would like to preferable import into PS8 instead to manually typing in data..an mdb would be perfect for this application...Many thanks
  4. 0
    Calvin Raju ·

    Hi Alexandre,Hope you are

    Hi Alexandre,

    Hope you are doing well.

    can you explain to me how to use thePs8 Import function please? or point me in the right direction.

     

    Thank you.

Log in or join to reply