Correcting actual dates
In the Open Standard
Carlos AranaMember for 17 years 4 months
- Created
- 1
- 5
0
Good day,
After entering actuals for an activity, a finish date is wrong: the activity is not finished but it got an actual finish date assigned. I tried to correct this by going to the performance archive and deleting the finish date, but the field can not be left blank.
How can I correct the activity's status to "Not finished"?
Thanks, best regards.
Carlos.