Importing/Exporting from/to CSV
- Created
- 11
- 1
Hello Vladimir,
I have created an Excell Macro that will generate an "oper" document and save it as a text tab delimited file, in order to import activities into Spider. I have set up the Macro to create for all activities all the "Standard" column values (I refer to the values of all the volums duration, ASAP, Split and so on) to have the default values of the single activity when creating a new project (Activity).
Everithing works great, but I have a question about the Identifier column. How does it's values affect the project, for example I saw that when creating a new project Activity 1 has the value of the Identifier equal to 28, when creating a new activity, the new activity will have the Identifire value 28 + 2 and so on. I also noticed that the Identifier value doesn't have to be unique.
Bottom line question, if in the oper.txt the Identifier field is equal to ""(nothing) or the same number (let's say 28) for all activities does this affect my results of sheduling, costs, assignments or any other results?
Regards,
Bogdan
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?