Diagrams and table reports
In the Open Standard
Evgeny Z.Member for 18 years 9 months
- Created
- 5
- 5
0
Dear all,
I am playing with diagrams and table reports now and have a couple of questions. Just checking, that that I understand the things correctly and not missing something:
- Both diagrams and table reports are possible to save as a template for future use
- Later on, it is possible to open saved table report template and a diagram and vise versa.
- Once table report is saved as a template, it is not possible to open this template and modify it. It is only possible to recreate it from the scratch and save it again with the same name, overwriting previous report with the same name.
- Unlike table template, it is possible to open diagram from the template, modify it and save again as a new diagram template or as the same diagram template.
- It is also possible to open table template as a diagram, modify and save again, however in this case it is not possible to modify all parameters of the table template
- It is not possible to see in the template what Activities have been included in the report and/or diagram template.
Regards.
Evgeny
5 replies
Oldest firstLog in or join to reply