Editing the TimeScale

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
3
3
0

Hello Planners,

Is it possible to edit the timescale in order to show Friday and Saturday as the weekly non-working days, instead of Saturday and Sunday?

I am using Spider 11.03.48, and I cannot get a convenient timescale for a project in Algeria.

Thank you, and Happy New Year

Alexandre

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi AlexandreSurely this is

    Hi Alexandre

    Surely this is done on the calendar using the appropriate work pattern.

    Also check that it is Friday and Saturday - not Thursday & Friday as it is in other MENA countries.

    Some companies only have the Friday holiday.

    Best regards

    Mike Testro

  2. 0
    Vladimir Liberzon ·

    Hi Alexandre,Thank you for an

    Hi Alexandre,

    Thank you for an idea. I expect that in the middle of January you will be able to select what days of the week to show as vacational. Look at what's new in Spider Project at our site. It could be done faster but we have long start of the year vacations here in Russia.

    I wish you Happy New Year,

    Vladimir

  3. 0
    Alexandre Faulx-Briole ·

    Hello Mike,Unfortunately, it

    Hello Mike,

    Unfortunately, it is not possible for time being, and Vladimir just confirmed the point. Concerning the non-working days in Algeria, I am pretty aware of it, as I have been working there for years.

    Hello Vladimir,

    Thanks for your answer; I am presently working on a technical paper about Spider Project for the Association Française de Normalisation (AFNOR); I should deliver the paper in French by the end of January.

    Cheers, Alexandre