Skills - Partial Workload

Bogdan LeonteMember for 14 years 2 months
Created
2
4
0

Vladimir,

I need a little help understandin partial workload and skills.

As far as I know (and tried) you cannot assign partial workload at the skill level, only at the resource level in the skill. when doing so Spider doesn't apply the partial workload if the skills have 100 workload, even though the resources inside the skill are set for partial workload.

However, if you assign the value of the minimal workload to the skill workload then Spider applies the partial workload to the rest of the activities.

Here are pictures:

1. Both activities with skills have 100 workload and partial workload to resource:

 

https://ibb.co/VWdXrQm

2. One activity has skill at the minimum workload of the resources and the other is at 100:

https://ibb.co/SdLdRL9

Best regards,
Bogdan

2 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Bogdan,it is possible to

    Bogdan,

    it is possible to assign partial workload to resource skill assignment.

    I cannot repeat your example. When I do it Spider Project selects two units of resource A to one activity and two units of resource B to another.

  2. 0
    Bogdan Leonte ·

    My mistake for incomplete

    My mistake for incomplete description:

    Resource A and Resource B will be named resources, say John and Mary.

    In order to schedule John and Mary and not 2 John or 2 Mary I used Resource Constrained Scheduling.

Log in or join to reply