Total Float take into account different calendars
In the Open Standard
Daniel MoraisMember for 8 years 5 months
- Created
- 6
- 4
0
Hi friends,
Today I did a simple testing take into account 3 activities and different calendars A (5WD) and B (7WD) and I had two different answers but, my question is, considering the CPM schedule we are limited to found a correct critical path according the calendar? What exactly happened?
Link file
Best Regards,
Daniel Morais
6 replies