Driving Predecessor/Succesor Filter

Bogdan LeonteMember for 14 years 2 months
Created
5
3
0

Hello,

I am trying to create a filter that would show only Driving Predecessor/Successor or both for an activity. Any suggestions?

Best regards,
Bogdan

5 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    In the Links table press

    In the Links table press right mouse button on the header of Driving column.

    In the pop-up menu select Filter by value and then select Yes.

    Return to the Activity Gantt Chart and in the menu select Filter/Filtered links only.

    Now you will see only driving dependencies in your schedule.

    Now press right mouse button on the row number of selected activity and in the activity menu select Filter/All preceding activities, All succeeding activities, both, or links with selected activity only.

    Filters can be cancelled in the Gantt Chart menu Filters.

  2. 0
    Bogdan Leonte ·

    Thank you Vladimir, Most

    Thank you Vladimir,

    Most helpful!

    Best regards,
    Bogdan

  3. 0
    Bogdan Leonte ·

    Vladimir, I may have

    Vladimir,

    I may have miskpoke, I would like to filter all preceding/succeding driving activities.
    When applying your procedure I still see activities that have non-driving links but the links are hidden.
    The filter should be composed of two conditions: 1. Driving Link + 2. Predecessor/Succesor.

    Best Regards,
    Bogdan

  4. 0
    Vladimir Liberzon ·

    Hi Bogdan,we will add this

    Hi Bogdan,

    we will add this next week. It is necessary to keep previous filter applying the next one. We missed this in this case.

  5. 0
    Bogdan Leonte ·

    Thank you for the insight and

    Thank you for the insight and implementation, it will be most useful!