 Hi there,


 have 2.sp files and both has been  exported form P6. one is baseline(No progress) and other is updated .
how can I assign the baseline over the updated one ?

Thank you

1 reply

Oldest first
  1. 0
    Renzo Constenla Bravo ·

    Dear colleague: proceed as

    Dear colleague:

     

    proceed as MR. PT Thomas described.

    Just take care that each activity in one file match with the right activity in the other file, through the Act ID.

    This is the only way for P6 to joint the current activity with its baseline.

    Regards 