Hello TILOS Gurus,

Is there a way to set proportions of annotations and task lines so they appear the same when you view a smaller portion of your project?

My project is a 135 kmtr pipeline divided into 3 separable portions. 1 & 3 are about 60kmtrs and 2 is about 15.

I've created a view of the overall project then one for each portion. As I am referencing the same tasks I'd like to be able to use them for each view, however what fits well in an A3 print out for the overall project is indeciferable for the portion 2 view.

When the 15kmtrs is stretched out across the same page as what was 135kmtrs, the task lines become very thin and annotations are too small.

I can use a work around where I find reasonable line size between the two views and create Layer filters for annotations but this is cumbersome and slow.

Any ideas??

Kind regards,

Craig Adams

2 replies

Oldest first
  1. 0
    Craig Adams ·

    Anyone there??

    Anyone there??

  2. 0
    Mike Testro ·

    Hi CraigI suggest that you

    Hi Craig

    I suggest that you contact the Asta Support Team 01844 261609

    Best regards

    Mike Testro