Recession and the role of Planner

Mohammed AzharuddinMember for 19 years 4 months
Created
16
3
0
What Do you think the role of planner in the recession environment
a) Advise the client to suspend the project and negotiate a revised contract price with Consultants and contracts
b) Go ahead with the project on agreed price and time
c) Advise the client to cancel the project
d) ........
e).....

16 replies

Oldest first
  1. 0
    Sunley Mathew, PMP ·
    Hi,
    You can advise the client to slow down works,
    Reduce the scope,
    Change marketing strategy from Sale to Leasing etc
  2. 0
    Ravi Potwar ·
    Prepared Cost driven Programme and Extend the duration of the project.
    Make aggerment with Contractor and Contractor for Payment schedule to pay accordingly for minimum Payment. No extention claim.
  3. 0
    Balu Karunakaran ·
    No EOT and LD.
  4. 0
    Milind Pandhare ·
    Lot of planners are loosing the job
    because of Slow down the work or suspension of the Jobs
  5. 0
    Balu Karunakaran ·
    But it seems things are picking up a bit.
  6. 0
    Shah. HB ·
    Of course may lay offs were there but now it got reduced and i found few openings in Abu Dhabi
  7. 0
    Milind Kulkarni ·
    hello,

    I can suggest here no need to reduce scope,you can suggest to Client to make payment partly.
  8. 0
    Shah. HB ·
    projects r moving on partial payments in UAE?
  9. 0
    Ravi Potwar ·
    Guys,
    Don’t much Worry ,jobs still comming up. Any one looking for the job, who has experience in Planning-Infrastructure and Mass Housing and looking to joined immediately please send your CV to ravipotwar@yahoo.com
  10. 0
    Shah. HB ·
    Openings are a lot in Saudi Arabia since they have massive projects i thrust they have started worlds tallest tower.
  11. 0
    Sachin Nair ·
    Some positive signs seen from Abu Dhabi and Qatar seeing the number of tender queries from there. Saudi - Kingdon tower ( tallest tower ) is still active. Role of planner in recession has increased much since now cash flow determines the progress and not the contractual milestone of completion. So from a resource = infinity situation, there has been a correction to resource = cash available.
  12. 0
    Mohammed Azharuddin ·
    Thanks All,

    I agree with the equation Sachin made and would like to ADD investor confidence to it. Hence

    Resource = Cash available + Investor Confidence.

    Ravi & Sunley made suggestions to safegaurd the clients bussiness by advising the slowing down of the project, reducing scope, changing market strategy, agreeing payment terms etc, But what about benefits to the Client? Do negotiating the price be an option.

    To my notice there are many projects which were up and running, where the cleint had either negotiated the price or replaced the PM’s, Consultants, Contractors for reducing the price and get benefit or rather reduce their loss.

    I beleive, Construction market too have a cyclic behaiviour with sellers and buyers market. It was sellers market upto 2008 and from 2009 it is buyers market. In the Project execution stage the seller is PM’s, Consultants, Contractors and other service providers, whereas the buyer is Cleint-Developer.

    This configuration may change in the Post Construction stage where developer takes the role of seller and the end user (general public, investors) becomes a buyer.

    So Guys in UAE I reckon its Investor Confidence which matters
  13. 0
    Mai Tawfeq ·
    hi guys:

    if any one can help to find a work in UAE , please tell me since our company is going to close within one month.


    regards.
  14. 0
    Shah. HB ·
    Hi mai

    Try registering in Bayt.com
  15. 0
    Abdul Azeem ·

    JOB

    All,

    I am working with Al futtaim carillion as a planning engineer in EMAL(Emirates Aluminuim, Aluminium smelter).

    I want to change a job with building construction.

    If any one have any openings for my needs please call me.

     

    Regards,

    Abdul

    0557894487

  16. 0
    Shareef Abdul Azeez ·

    I believe UAE has to follow

    I believe UAE has to follow the path of Kuwait & Bahrain to tackle Recession.......

     

    http://gulfnews.com/news/gulf/kuwait/kuwait-to-scrap-sponsorship-system-1.687703

    http://gulfnews.com/news/gulf/kuwait/kuwait-firm-on-decision-to-scrap-sponsorship-system-1.691514

    http://gulfnews.com/news/gulf/bahrain/qatar-could-follow-bahrain-in-scrapping-sponsorship-system-1.2090