24 May 2024 Project Controls News

Dear Planning Planet Member,Join the Global Community - welcome to the newsletter; did you know that this newsletter goes to the largest project controls commun

Dear Planning Planet Member,

Join the Global Community - welcome to the newsletter; did you know that this newsletter goes to the largest project controls community on planet Earth? 

NEW PARTNER - WATCH THIS SPACE!

We are really excited and looking forward to sharing their news and solutions with you all (coming this week!) - moving us into a world of generative scheduling; upload your baseline P6 or Oracle Primavera Cloud schedule and ALICE Core will simulate scenarios to look for optimized schedules with better outcomes.  Check them out...

TOP 5 CONTRUENT ENTERPRISE RELEASES YOU SHOULD KNOW ABOUT

Register to recieve a live recording...

In this session, you’ll discover:

  • Magic Grid: Dubbed the ultimate spreadsheet killer, this powerful tool enables our customers to swiftly identify potential issues before they go out of control.
  • Contract Dashboards: Gain enhanced insights and reporting capabilities with our comprehensive PowerBI Dashboards.
  • Data Warehouse Automation: Simplify data-pushing processes for accurate dashboards, ensuring seamless integration and efficiency.
  • Replica Data Base: Access live operational data for enhanced reports and dashboards, optimizing performance without compromise.
  • Multi-Tenant Reporting Service: Experience improved data processing and delivery with reduced report generation time by two-thirds.

Don’t miss this opportunity to stay ahead of the curve and explore the future of project controls with Contruent Enterprise.

TACTICS TO SUCCESSFUL SOFTWARE IMPLEMENTATION: A COMMON AGREED VISION, COUPLED WITH STRONG LEADERSHIP.

Implementing industrial software can revolutionise operations, streamline processes, and boost productivity. Yet, the journey from selecting a software solution to achieving full utilisation has many challenges. The secret ingredient to a successful implementation? While there isn’t a one-size-fits-all solution for every organisation, certain tactics can significantly enhance the likelihood of success. Drawing from over two decades of software implementation experience, IAMTech shares insights on avoiding common mistakes within the software integration process.

In our last newsletter, we emphasised the importance of stakeholder involvement, engagement, and empowerment from the outset of any software project. This week, we explore the need for a common, agreed vision coupled with strong leadership—integral components for any successful software project.

Articulating a Clear Vision

A clear vision is the cornerstone of successful software implementation. 

“If you can’t articulate your vision at the beginning of every meeting within 20 seconds, it’s too complicated.”  

Simplicity is key. A straightforward Vision ensures that all stakeholders are aligned and moving towards the same goal.

The vision sets the direction and defines what success looks like. It provides a common purpose that motivates and guides the project team. Without a clear vision, projects can quickly become fragmented, with different stakeholders pulling in different directions. This misalignment can lead to delays, increased costs, and ultimately, project failure.

Creating a vision requires input from all key stakeholders. Engage them early in the process to gather their insights and perspectives. This collaborative approach not only helps in crafting a comprehensive vision but also fosters a sense of ownership and commitment amongst stakeholders.

The Role of Strong Leadership

Once the vision is established, strong leadership is essential to drive it forward. Leaders play a critical role in maintaining focus, facilitating decision-making, and ensuring that the vision is translated into actionable plans.

Strong leaders are decisive, resilient, and excellent communicators. They can navigate complex challenges, manage diverse teams, and maintain momentum even in the face of setbacks.  They can make tough decisions, especially when there is no clear consensus among stakeholders.

Consider a multinational energy company implementing software across all its assets worldwide. The company’s vision is to have a standardised process for Shutdowns, Turnarounds, and Outages (STOs), accepting a 10% variation for local or regional differences. This clear vision provides a solid foundation. However, without strong leadership to drive this vision, the project can falter.

For instance, when defining the "to-be" business processes, leaders must be strong enough to make decisions, even when a consensus is hard to achieve. If leaders allow endless debates without making firm decisions, the project can become delayed in indecision and conflict. 

“Effective leaders view discussions as opportunities to gather diverse experiences and insights from different sites and use this information to inform their decisions and improve the projects outcome.”

Avoiding Common Pitfalls

Here are just a few common pitfalls in software implementation projects, and how to avoid them:

1)     Lack of a Clear Vision

A vague or overly complex vision can lead to confusion and misalignment. Ensure your vision is simple, clear, and easily communicated.

2)     Inadequate Leadership

Weak leadership can result in indecision and lack of direction. Invest in developing strong leaders who can drive the project forward with confidence.

3)     Insufficient Stakeholder Engagement

Stakeholder engagement is crucial for buy-in and successful implementation. Engage stakeholders early and regularly throughout the project.

4)     Resistance to Change

Change can be challenging, and resistance is common. Address resistance by communicating the benefits of the new software and providing adequate training and support.

5)     Overlooking Local Differences

While a standardised approach is beneficial, it’s essential to acknowledge and accommodate local or regional variations. This flexibility can enhance acceptance and usability of the software.

Successful software implementation is not a matter of luck. It requires a clear vision, strong leadership, and strategic engagement of stakeholders. By articulating a simple, compelling vision and empowering leaders to drive this vision, organisations can navigate the complexities of software implementation and achieve transformative results.

At IAMTech, we are committed to helping our clients avoid the common pitfalls that can impede a successful software implementation. With over two decades of experience, we understand the challenges and more importantly know how to overcome them. Will you make your best decision today and contact us to learn more?

This newsletter has been based on ‘Secrets to a Successful STO’ a talk by Ross Coulman (MD, IAMTech) and any quotes are attributed to him. 

Or alternatively enjoy the above on YouTube...

UNDERSTANDING ORACLE PRIMAVERA P6 ACTIVITY % COMPLETE

Understanding Oracle Primavera P6 Activity % Complete

 

The P6 Percent Complete type should be understood if it is intended to be used to update (status or progress) the schedule. 

In summary the default for new activities is set in the Percent Complete Type drop-down box and this option may be set for each activity individually after it has been created. 

Default Percent Complete Type

The Default Percent Complete Type for each new activity in each project is assigned in the Defaults tab of the Details form in the Project Window:

 

 

The Percent Complete Type of a new activity is set to the Default Percent Complete when created and may be changed at any time in the Activities window.

Percent Complete Types

  • Physical % Complete – This field enables the user to enter the percent complete of an activity and this value is independent of the activity durations and no summary values are calculated.
  • Duration % Complete – This field is calculated from the proportion of the Original Duration and the Remaining Duration and they are linked. A change to one value will change the other. When the Remaining Duration is set to greater than the Original Duration this percent complete is always zero.
  • Units % Complete – This is where the percent complete is calculated from the resources’ Actual and Remaining Units of Labor and Non Labor resources only. A change to one value will change the other and when more than one resource is assigned then all the Actual Units for all resources will be changed proportionally. This will be covered further in the Updating Resources chapter. This is similar to the Microsoft Project % Work Complete.

Activity % Complete

The Activity % Complete field is linked to the % Complete Type field assigned to an activity in the General tab of the Details form in the Activities Window or the % Complete Type column:

The Activity % Complete is also linked the % Complete Bar and this value is represented on the % Complete Bar.

Eastwood Harris Learning Resources

Accelerate your understanding of scheduling software to advance your scheduling career and be able to prepare better schedules with Eastwood Harris books, training courses and online videos on the following software packages:

  • Microsoft Project,
  • Oracle Primavera P6 and 
  • Elecosoft (Asta) Powerproject
Online videos available through Udemy by following these links:

Please follow these links:

  • Eastwood Harris books and training materials are available here 
  • Eastwood Harris inhouse, one-to-one and public training courses are offered through Primaskills Pty Ltd, more details here>>>>.
  • Resources for Oracle Primavera P6 users such as third party software that works with P6 and technical papers on Primavera P6 at our Primavera Portal.

Paul E Harris
Director Eastwood Harris Pty Ltd

BEYOND PDF's

 

Join our free online webinar organized by Proadvise and Synami!

The webinar will provide a detailed overview of ScheduleReader, the software for viewing and analyzing data from XER and XML project schedules created with Primavera P6.

Learn more...

CLEOPATRA ENTERPRISE WILL TAKE THE STAGE AT THE AACE INTERNATIONAL CONFERENCE & EXPO 2024

Babette Schep will talk about the importance of having an integrated tool like Cleopatra Enterprise in the dynamic landscape of project management

What to expect from this presentation? With Cleopatra Enterprise, how project managers can: 

  • Streamline the project management by centralizing all project data and documentation 
  • Generate detailed cost estimates quickly and accurately 
  • Manage costs throughout the project lifecycle and more... 

Stop by Cleopatra booth 408 for questions and details.

ON-DEMAND WEBINAR | UNLOCKING STO POTENTIAL IN THE MIDDLE EAST: THE POWER OF DIGITIZATION

Cleopatra Enterprise is looking back at the successful webinar featuring their strategic partner in the region, Interactive UAE. Watch this webinar throwback to grasp how to reshape STO management through digitization in the Middle East via practical examples.

Interested in learning more? Meet the Cleopatra experts in person at the STOTme 2024 Al Khobar (Booth 27)

Watch now...

READY TO DIVE INTO THE COMPLEXITIES OF WELD MANAGEMENT DURING TURNAROUNDS?

Read Cleopatra Enterprise’s latest blog, "The Complexity of Weld Management Processes in Turnarounds", where their Senior Implementation Consultant, Jordy Palit, shares insights on: 

  • The critical role of welding in ensuring the integrity and longevity of industrial assets during maintenance and overhaul periods. 
  • Strategies and best practices to boost efficiency, safety, and productivity, from thorough pre-turnaround planning to comprehensive post-turnaround evaluation. 

Read the full blog...

VIEWER FOR XER and XML SCHEDULES

Jabel Oil Services and Synami are organizing a free online webinar dedicated to providing a detailed overview of ScheduleReader, the leading viewer for XER and XML schedules.

ScheduleReader is a software tool that allows users to open project schedules in formats such as XER and XML, without the need for the original scheduling software. The software enables users to visualize the project schedules that are exported from the Primavera P6 application, as well as conduct various analysis and create dynamic reports.

Learn more...

 

A SUPERIOR ALTERNATIVE TO THE "MOST POPULAR" SOFTWARE FOR US AS PLANNERS?

 

A superior alternative to the "most popular" software for us as planners?

Spider Project

Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.

Check it out here...   Ask questions here...

Construction CPM Conference 2025 

Our early early bird ends May 31st, so REGISTER before $775 rate ends. See here...

WOULD YOU LIKE TO ADVERTISE ON PLANNING PLANET?

We want to give more of our members the opportunity to advertise on our site. Click here to get started!

THANK YOU FOR READING OUR MESSAGES

If you'd like to help the small but enthusiastic team of people helping with this newsletter please do get in touch with us via ppadmin@planningplanet.com   We know we have a long way to go to make this informative and an anticipated bi-weekly "read" so do get in touch and get involved.  

Regards... 

The Planning Planet Team

To  unsubscribe please email ppadmin@planningplanet.com please ignore the unsubscribe link below

That's all folks....