Resource Modelling
- Created
- 3
- 5
Hi all,
I work for a groundwork’s sub-contractor and looking to advance our overall planning capability. Use of Asta has been basic up to now. I have started to resource load our programmes and model based on outputs per hour to generate the duration on individual tasks. Really, just playing with the software “learn as you go” to get to this point.
A couple of questions from doing this first time around;
1. Is it possible to create a standard task library with resources pre loaded with the outputs etc. (gangs) that could be dragged and dropped onto tasks so we are not repeating the same on every new project. Say excavating and installing 110mm drainage for example.
2. Is there a function which can work out the resourcing of the project based on a constraint on either labour/plant cost or hours? I.e if we have 100 machine hours priced, constraining the project so the plan does not extend beyond that - or if it does, something flags the issue?
Many thanks for any assistance
3 replies
Oldest firstLog in or join to reply