Microsoft Project Export

Jim OBrienMember for 23 years 2 months
Created
1
29
0
Can anybody help with tips for importing Microsoft Project data into Powerproject. (Also for exporting). I can’t seem to find any easier way than cutting and pasting from Project and then checking everything matches up by hand.

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello,
    which release of PowerProject are you using?
    Astadev has developped a set of macros that installs a tool bar in both PP8 and MSP to generate "non standard" XML files. I mean you cannot use the MSP "save as" feature to pass your project into PP8, only the PP8 macro.
    Contact Asta Support about that.
    Regards,
    Alexandre