MSP -v- P3 -v- Powerproject
In the Open Standard
DB
David BordoliMember for 24 years 6 months
- Created
- 96
- 6
0
I read with interest the previous discussion regarding MSP –v- P3 (I couldn’t reply on that thread for some reason).
I have recently become embroiled a little in this debate when discussing the merits (?) of MSP when a colleague said :
Touching on the future, we need to be aware that MSoft has done a licensing deal with the UK government on all its products, and I am now beginning to see public sector clients requesting programmes in MSP. This wont go away of course, so is there a simple way forward?
This all came about because MSoft have dropped the .mpx format that was used by many software developers as a relatively simple way of allowing data to be transferred between different project management software. Our dilemma was that, as users of Asta Powerproject, MSP files were inaccessible and we didn’t want to regress to using MSP in parallel.
I spoke to the friendly people at Asta (try doing that with MSoft!) and their reply was:
I also know that we live in Microsoft world and they have made life a little more difficult by allowing MPX import, but disabling MPX export from MSP 2000/2003. So you can send someone a project from Powerproject in an MPX format - and they can open it. They cant send it back though!
So for that reason we have developed (and give away) an Add-In to Powerproject and MS Project that reads & writes to a common XML file format.
I have asked our Help Desk to put on a CD and send to you. You can freely distribute this within Buro4 and its clients.
We were also discussing ‘Programme Management’ (as in the management of a portfolio of projects:
We [Asta] have been very successful recently with various collection of projects in a single database - to allow cross-project reporting. This is where Powerproject scores over MS Project as it is essentially a collection of dispersed projects, rather than a coherent whole. The only really serious completion is P3e, but it is at least 3-times more expensive than PP! For this to work effectively we developed Asta Site Progress - for remote (cheap) progress feedback.
The final comment was:
Even in MSP 2003 they have the fantastic fundamental flaw of only allowing one link between two tasks. ie you cannot have a SS and FF between the same tasks - so once one has started there are no restraints! The output is also pretty poor, and of course only one task per line, etc...
My apologies if this has sounded like an advertisement for Asta Powerproject but I think we should all be aware there is useful project management software around other than P3 and MSP!
Asta Developments can be contacted at Asta Developments
Regards
David
dbordoli@burofour.co.uk
To find out mor about Buro Four visit us on the web
I have recently become embroiled a little in this debate when discussing the merits (?) of MSP when a colleague said :
Touching on the future, we need to be aware that MSoft has done a licensing deal with the UK government on all its products, and I am now beginning to see public sector clients requesting programmes in MSP. This wont go away of course, so is there a simple way forward?
This all came about because MSoft have dropped the .mpx format that was used by many software developers as a relatively simple way of allowing data to be transferred between different project management software. Our dilemma was that, as users of Asta Powerproject, MSP files were inaccessible and we didn’t want to regress to using MSP in parallel.
I spoke to the friendly people at Asta (try doing that with MSoft!) and their reply was:
I also know that we live in Microsoft world and they have made life a little more difficult by allowing MPX import, but disabling MPX export from MSP 2000/2003. So you can send someone a project from Powerproject in an MPX format - and they can open it. They cant send it back though!
So for that reason we have developed (and give away) an Add-In to Powerproject and MS Project that reads & writes to a common XML file format.
I have asked our Help Desk to put on a CD and send to you. You can freely distribute this within Buro4 and its clients.
We were also discussing ‘Programme Management’ (as in the management of a portfolio of projects:
We [Asta] have been very successful recently with various collection of projects in a single database - to allow cross-project reporting. This is where Powerproject scores over MS Project as it is essentially a collection of dispersed projects, rather than a coherent whole. The only really serious completion is P3e, but it is at least 3-times more expensive than PP! For this to work effectively we developed Asta Site Progress - for remote (cheap) progress feedback.
The final comment was:
Even in MSP 2003 they have the fantastic fundamental flaw of only allowing one link between two tasks. ie you cannot have a SS and FF between the same tasks - so once one has started there are no restraints! The output is also pretty poor, and of course only one task per line, etc...
My apologies if this has sounded like an advertisement for Asta Powerproject but I think we should all be aware there is useful project management software around other than P3 and MSP!
Asta Developments can be contacted at Asta Developments
Regards
David
dbordoli@burofour.co.uk
To find out mor about Buro Four visit us on the web
96 replies
Oldest first- 0BEBernard Ertl ·[quote]Even in MSP 2003 they have the fantastic fundamental flaw of only allowing one link between two tasks. ie you cannot have a SS and FF between the same tasks - so once one has started there are no restraints![/quote]
It can be argued that allowing FF restraints as mentioned above is not compatible with the critical path method. See the What relationships are compatible with the critical path method discussion.
IMHO, claiming the lack of a hammocking (or even just the lack of FF relationships for that matter) is a fundamental flaw is quite a reach. But I guess it depends on whether you are painting pictures or performing critical path analysis...
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0DBDavid Bordoli ·Bernard…
Thank-you for your forthright contribution. I am relieved that your statement is IYHO and IMHO a ‘discussion’ requires more than one contributor or opinion – but hey, lets not be pedantic here. However, I do take a little exception to your veiled critism and suggestion that I may be painting pictures rather than performing critical path analysis.
Even though I started using critical path analysis in the construction industry a mere 25 years ago I have never come across anyone who used Activity-on-Line, even way back then we were using Activity-on-Node and sending the stuff away to be computer analysed.
Things, and methods have developed and improved a bit and we can’t always depend on Classical Theory – I know some people do still subscribe to the world being flat but hey ho…
And who mentioned hammocking? I seem to remember that without the use of dummy activities A-o-N depends on ‘FS dependencies’ only. I almost can’t be bothered with this ‘discussion’ it is so facile! If you advocate the use of SS dependencies then you must also have FF dependencies (or at least a FS or imposed finish tying down the end). If not it is impossible to have a critical path – when I construct a programme (schedule?) I try to ensure the project has one start date and one end date and all activities have a start dependency and a finish dependency.
IMHO, again, I tend to think that Richard Ormerod at Asta does know what he is talking about. Serious planners could do worse than read his seminal paper on simulation (Bennett J & Ormerod R N. Simulation Applied to Construction Projects. Construction Management & Economics, vol 2. E & F N Spon, 1984). In there you might just glimpse the first demonstration of ‘linked bar charts’ and their use in critical path analysis – exactly the sort of thing that virtually all project management software uses as it’s preferred method of communicating the plan.
Whilst knowing nothing about ’eTaskMaker™ project planning software’ I am beginning to wonder if I touched a raw nerve?
Regards
David
dbordoli@burofour.co.uk
Visit Buro Four on the web
- 0BEBernard Ertl ·David,
It looks like I am the one who touched a nerve. Sorry to ruffle your feathers (so to speak).
...IMHO a ‘discussion’ requires more than one contributor or opinion...
Agreed. Im looking forward to more participation on the issues raised. The topic I linked is still fairly new.
I do take a little exception to your veiled critism and suggestion that I may be...
I made no criticisms or suggestions targeting you. My comments were directed towards the use of FF relationships (in general) which require calculating early starts "backwards" - which is contrary to the definition of the critical path method. The integrity of early start/early finish is compromised when there is more than one basis (as mentioned by Bramble and Callahan).
And who mentioned hammocking?
Sorry, I was being too loose with terminology. I meant tasks/activities that used both a SS & FF relationship between them.
If you advocate the use of SS dependencies then you must also have FF dependencies (or at least a FS or imposed finish tying down the end). If not it is impossible to have a critical path ...
As mentioned previously, early starts for FF relationships must be calculated in a reverse direction (which is incompatible with the definition of the critical path method). In cases where a SS relationship is used, I agree that a FS relationship must be used to establish the end point relationship for the task within the logic network.
... exactly the sort of thing that virtually all project management software uses as it’s preferred method of communicating the plan ...
I am aware that PDM scheduling is popular. That does not provide a logical basis for claiming that the lack of ability to use of a SS & FF tie between two activities is a fundamental flaw. I believe I have taken a position of arguing fundamentals when I am discussing the application of scheduling relationships with regards to the critical path method.
My comments are not personal or related to any particular software. I am merely pointing out what is IMHO, an unfair characterization.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0FGForum Guest ·Firstly, In response to David, I have always used Activity-on-Arrow networks during my 25 or so years. Even in my current role, we went away from the corporate PDM tool to one that supports ADM purely because those who really dont give a hoot about plans but are an integral part (ie the assigned resources) thought that ADM was the simplest to understand. This is a key element in our attempts to get the all important buy-in so projects could (and indeed were) completed in acceptable timescale. The use of hammocks (sponge) is limited to management and Support activities for cost purposes only.
Secondly, To get back to the original subject: On a technical note which aggregation algorithm do MSP/P3/Powerpoint use?
I know that MSP certainly used a serial one at one point as opposed to the parallel algorithm. If a project is time-constrained, it is a must that the tool will give optimised results.
- 0DBDavid Bordoli ·Bernard…
Whilst I have more important things to do than respond I do not wish to give the impression of tacit acceptance of what you say.
I think if you wish to sling around such comments as “But I guess it depends on whether you are painting pictures or performing critical path analysis...” you should be more considerate of your language – maybe you meant, “… it depends whether one is painting pictures … “. I think you will agree that there is a world of difference in the direction of these two statements.
On first reading I do not quite understand what you mean by FF relationships require calculating early starts ‘backwards’. I thought early starts (or earliest times) were calculated on the forward pass and late starts (or latest times) on the backward pass.
In the extract from Bramble and Callahan that you cite I see no discussion on the integrity of early start/early finish. They appear to be considering the values of start float, activity float, and finish float which are an important factor in their discussion of Construction Delay Claims.
Having said that the comment that I originally reported was “MSP 2003 they have the fantastic fundamental flaw of only allowing one link between two tasks. ie you cannot have a SS and FF between the same tasks”. As you can see this is related to a particular software. One, which as I understand does not subscribe to your view of classic definition of a critical path method scheduling. In that case, and in relation to the methods it employs to schedule projects, calculate critical paths etc, I am in agreement with Richard Ormerod that it is a pretty fundamental flaw.
As you know the legal profession’s view of scheduling is not the same as the pragmatic view required by practitioners. Questions of float are important but there is already a view (in the UK at least following the publication of the SCL Protocol) that practitioners will modify the way they construct networks to eliminate float to protect them during potential disputes but, as a consequence, will reduce their flexibility in carrying out the works.
We have to move on. As an analogy; Newton’s Laws of Motion took over from the Greek and other philosophers views of time and motion and even now Einstein’s Theory of Special Relativity has revisions. Classic theory is only good until a new classic theory comes along. I think it is probably time to move on from the developments of 1958/59 – techniques had to be relatively simple then, without number crunching computers the theory and practice was necessarily simple to match the resources of the time.
I think we will have to agree to disagree on this.
Regards
David
dbordoli@burofour.co.uk
Visit Buro Four on the web - 0DBDavid Bordoli ·Hi Forum Guest
Thanks for your comments… I was beginning to think this was an insignificant battle of semantics between Bernard and I!
You are absolutely correct about buy-in. In the UK Construction Industry at least bar charts are the norm for communicating plans upwards and downwards. I suppose it depends on the target of your audience but few in my industry would understand an A-o-L or A-o-N diagram.
I am not absolutely sure about your second point (it’s Powerproject by the way!) but I’ll do my best to get an answer for you.
Regards
David
dbordoli@burofour.co.uk
Visit Buro Four on the web. - 0BEBernard Ertl ·... you should be more considerate of your language ...
Yes, I concede, I did not phrase that well. Please accept my sincere apology. I am sorry.
On first reading I do not quite understand what you mean by FF relationships require calculating early starts ‘backwards’. I thought early starts (or earliest times) were calculated on the forward pass and late starts (or latest times) on the backward pass.
Yes, but PDM systems are calculating the early starts "backwards" for FF & SF relationships on the forward pass.
The FF relationship in most PDM implementations determines the early start for a task. This can only be accomplished by using a backwards calculation from the related task as the anchor. Thus, the early start calculations have two (or more) possible basis points if FF relationships are used within the logic network. See Joe Mansours post in the Contiguous or Interruptable thread for more background on the pitfalls involved in this.
I believe that it is possible to construct a network schedule without concurrent SS & FF relationships that represent the same structure. That is why I believe that the characterization of a "fundamental flaw" is unfair (regardless of what software the original comment was targeting).
I think we will have to agree to disagree on this.
Agreed.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0FGForum Guest ·The formula I referred to earlier is in fact the heuristic algorithm (possibly Polynomial.)
The point I was making about this was that MSP certainly didn’t use it in earlier versions (upto MSP 2000) and was trying to ascertain whether P3 and Powerpoint do, as for time constrained projects it is a vital tool to use so the optimised solution is known.
My personal opinion is that presentation of detailed barchart is the worst format to ’pass downwards’ but this is obviously dependant on activity numbers - I am of the old school that believes in Multi-level plans each targetted at various levels of the organisation. - 0FGForum Guest ·Hi PPers,
Following some lively interest in the ’Powerproject’ subject we have now created a new Forum Category especially for you Powerproject Guru’s.
We hope that this will be of interest to you?
Regards. - 0DSDaya Sugunasingha ·IMHO I agree with every word of David Bordoli’s post and subsequent reply.
Those of you who may have used Microplanner in years gone by would agree that it did used activity on the node networks.
I also wonder if Bernard Ertl thinks that Power Project and Power Point are the same product?
Daya - 0BEBernard Ertl ·Daya, where have I posted anything specific to Power Project that could support your musings?
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0GCGavin Clegg ·Bar Charts are easily read by all, from Project Manager to the Man/Woman at the "coal face". They can be modified and formatted to show v.detailed work on less paper (GOOD FOR TREES) and can be marked up by hand to show as-built dates including delays.
Lets not make planning / programming too complicated. We need to give a clear message to all in a "Contract Team" - not everyone is an expert in understanding complex structures / logic.
Regards
Gavin - 0GCGavin Clegg ·Another quick note.
I have no experience of P3, but use Suretrak (Because the client wants like it!). I do use MSP because our M+E department produces all there programmes in the format.
But, I maintain that Powerproject is the most easy to use out of all three and produces well presented programmes that ALL understand.
My Votes with Powerproject.
Regards
Gavin - 0DSDaya Sugunasingha ·Dear Bernard Ertl
On the 12 November 2003 you posted this in reply to David Bardolli posting ....
"IMHO, claiming the lack of a hammocking (or even just the lack of FF relationships for that matter) is a fundamental flaw is quite a reach. But I guess it depends on whether you are painting pictures or performing critical path analysis..."
Did you mean using Powerproject as akin to painting pictures, if not I appologise.
Powerproject can be used as a very basic bar chart drawing tool, but if used as it is intended, it can do all you want usually .... if not ASTA does give the user the opportunity to influence the development of the software and you cannot say that for many of the others
Regards
Daya
- 0BEBernard Ertl ·Hi Daya, no I was not talking about any specific software. I mentioned this at the end of my second post to this thread.
I was responding to a general claim. I think if you read my subsequent posts in this thread (to the first one which you took the quote from) you will see that I discuss the issue of the PDM FF construct in a general sense. For the reasons I already mentioned, I do not believe that it is a "fundamental" requirement for critical path scheduling.
The SS & FF relationships between two tasks can be modeled using SS & FS relationships (to the second task’s successors). Convenient <> Fundamental
Perhaps the painting pictures comment was a little strong. It sure made for an interesting discussion though.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0DSDaya Sugunasingha ·Hi Bernard
Thank you for the comment.
A "fundamental" requirement for critical path scheduling is closing the network and not leaving Activities dangling, unless there is a reason for doing so. If for example one had a string of activities all linked in accordance to its logic with FS I think that would be fine. On the other hand if one used SS the I feel it need to be closed with a FF or visa versa, don’t you agree.
Regards
Daya
- 0BEBernard Ertl ·
- Originally posted by Bernard Ertl earlier in this thread:
In cases where a SS relationship is used, I agree that a FS relationship must be used to establish the end point relationship for the task within the logic network.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software - 0FGForum Guest ·Hey all!!!
Sorry i am only a guest have been trying to join for days but it just wont let me for some reason!!!! Oh well!
To vere away from the technical issues you guys have discussed and to get back to the real heart of this thread may i just say that whilst Powerproject Teamplan is usable i must back the corner of P3 and Suretrak. I have now used both PP5 & 7 and although i can see the dramatic steps being taken i still find that in certain aspects it falls short of P3/suretrak.
A demonstration of my critisism is the visual aspects of PP/TP, to my knowledge you are unable to show target bars for each activity whereas showing Target bars in P3 is both easy to do and indeed to view. I think that at the end of the day the software has to show things in a particularly good manner, PP/TP however i find falls short on the display of information aspects.
Another one and again this maybe my lack of knowledge but i am not a great fan of the way progress shading is shown on the activity bars, can this be changed?????
Alistair Sharp
- 0GCGavin Clegg ·Forum Guest,
Thanks for your comments but any number of baselines (Target Bars)can be shown against the actual worked activities. They can also be compared against actual work to show end variance (slippage) to produce a Progress Table.
We update and re-baseline each time the programme is revised, but we still need to compare the completed as-built against the original baseline programm not just the latest revision.
Suretrac does not allow this - you can only view one set of target dates. Does P3 allow this ??? I have never used it.
- 0DODarrell ODea ·Daya,
If what you are comparing functionality wise, is to TP or PP. Where Functionally is concerned, in my opinion, TP/PP falls down in many other ways. (Hey, & no disrespect intended, this is just an opinion).
Regards,
Darrell
This last reply is on the defence.
I think that if you have to go into another software to do any function that should be part of your original planning software IT IS A FAILURE IN FUNCTIONALITY!
Daya - 0DBDavid Bordoli ·I have just found another independent academic Project Planning Software Review:
Heesom, D. and Mahdjoubi, L (2002). Technology Opportunities and Potential for the Virtual Construction Site, Volume 2, Project Planning Software Review. Built Environment Division, University of Wolverhampton. EPSRC Grant No GR/N00876. ISBN: 1-86162-0002-0.
The results (titled ‘Functionality of CPA Software) are:
MS Project 115
Powerproject 110
Primavera 103.3
Dekker TRAKKER 100
Project Schedule 96.5
OPX2 Pro 93.3
Planview 90
Turbo Project 88.2
CA-Superproject 86.6
Pertmaster 83.3
Realtime Projects 83.2
MicroPlanner Xpert 44.9
Some might find MS Project being #1 a little perverse in that it can only handle one dependency between two tasks! Also there is an erroneous assumption in the scoring that a file exchange format ‘Microsoft Project Database’ (MPD) is a ‘de-facto’ standard whereas clearly it is not; only 3 of the 12 products use it, one of them being MSP. If that scoring is removed the results change:
Powerproject 110
MS Project 105
Primavera 103.3
Dekker TRAKKER 100
Project Schedule 96.5
OPX2 Pro 93.3
Planview 90
CA-Superproject 86.6
Realtime Projects 83.2
Turbo Project 78.2
Pertmaster 73.3
MicroPlanner Xpert 44.9
There were two areas where Powerproject scored higher than Primavera:
Q2. Primavera allows 0-100 WBS (scoring 3.3 points) and Powerproject allows over 1000 (scoring 10 points).
Q4. Primavera allows 20000-100000 tasks (scoring 6.6 points) and Powerproject allows over 100000 tasks (scoring 10 points).
I know the maths don’t add up, there should be a 10 point difference, not 7.7 and I have no idea of the accuracy of other elements - I’m just the messenger!
Regards
David
dbordoli@burofour.co.uk
Visit Buro Four on the web
- 0AAAsif Anwar ·Dear Planners
Being a user of P3/Microsoft Project for almost 10 years and Power project recently, I have found that while PP is good for tendering purposes, it lacks behind P3 when it comes to the actual monitoring of the projects during construction phase and when preparing the resource/cost reports and histograms. P3 is ahead of MSP and PP in this regards.
Other features of presentation are more or less same for all 3 softwares.
Regards
Asif - 0AFAndrew Flowerdew ·To input and generally use - got to be PP.
To monitor a project and get usefull data out of - P3.
Cost - PP
Support you can talk to - PP
Client base usage or requirement in UK - P3
I really would like to say PP is the best, I use it more of the time exactly because it easier to use but somehow it often has that annoying habit of not quite giving you what you want.
Hard choice, for the money PP but somhow P3 has often just got that edge when you need it. - 0DSDaya Sugunasingha ·What we need is to be free to interchange data from one software package to the other easily and without the risk of losing some incompatable data in the process.
But I suspect that the software houses in there aim to corner as much of the market for themselves don’t see it that way and usually make it very difficult.
Why was the MPX facility in Project 2000 onwards discontinued?
- 0PJPhilip Jonker ·Hi David,
Sorry for the late reply, as the thread has just been re-surrected, but I think Messrs Heesom, D. and Mahdjoubi must have been some academics, that had no experience of practical planning, according to the their ratings of software. In fact brain dead may cover their answers better. Probably a couple of marketing surveyors, who have been smoking some strange green stuff. - 0BEBernard Ertl ·Daya, the MPX format was limited in the data that it stored and the structure for it too. AFAIK, PMI is working on an open schema for project data. I don’t know when it might be published or implemented by vendors (or even if it will be adopted).
Bernard Ertl
eTaskMaker Project Planning Software - 0AFAlexandre Faulx-Briole ·Daya,
Microsoft replaced the MPX project exchange format with MPD (aka Microsoft Project Database), only used to agregate several MSP plannings in one database; and MDB (MS Access database).
PowerProject cannot open MPD files, and does not recognize MSP generated MDB files.
Therefore, the only way to transfer a project planning from MSP to PP is to create a MPX file. As MSP 2K and above do not know MPX, you will use Sciforma MPX2000 or something alike.
All the best
Alexandre Faulx-Briole - 0GCGavin Clegg ·Just a short reply to MPX conversion. If you use V7 or V8 of powerproject you can obtain a macro from Astadev that will set up a button on your toolbar. This allows export and import of MPX programmes in both PP and MSP.
NB Also....
V9 of Powerproject will include this built in. Due to be released end of the year.
Regards
- 0BEBernard Ertl ·Daya, you can find Sciforma’s MPX2000 here:
MPX2000
Bernard Ertl
eTaskMaker Project Planning Software - 0ABAlistair Blakey ·"Just a short reply to MPX conversion. If you use V7 or V8 of powerproject you can obtain a macro from Astadev that will set up a button on your toolbar. This allows export and import of MPX programmes in both PP and MSP."
A word of warning: check the dates once the import/export is done - it is not perfect and large discrepancies can be found. - 0DSDaya Sugunasingha ·Each to his own!
When you get used to using a certain piece of software you get to know how to set it up best from the begining and get round it’s weaker points and really make use of it stronger points and you can do it quicker then if you used software you don’t know too well because it presents too much of an effort to change to something different and new or you do not enough time to do so because of pressure at work to produce results asap.
Best of Luck
Regards
Daya - 0PJPhilip Jonker ·Hi Bill,
The old Open Plan v4 (Dos) was probably better, as you had more access to the database files, including codes,etc. But since they killed that one of, P3 has probably been the best replacement since then. However, with the advent of the so-called P3e and P3ec, and the latest one I saw two days ago, version P4, which is a for of P3e/ec, They are going in the wrong direction. I think the problem is a lack of marketing and as such input from users (in this case happy users).
Regards
Philip - 0DSDaya Sugunasingha ·Dear Bill/ Philip
I have not used the latest Open Plan or P3ec and can only think that they must have done their market research before abandoning the DOS versions.
To a question for help on choosing soft ware I did give Tim Readman the following personal view from my experience in the past.
I think there is no indication that they will be reverting back to it unless market trends reverse.
This is what I sad to him.
"I hope you make the correct choice for your company.
I am an advocate of Powerproject as they have consistently listened to the wishes and needs of the man on the work face "THE PLANNER" and improved and developed it accordingly. But you have to examine both or all other software available and chose the one that delivers the end produce you require.
I have been in the field of construction planning since the days before computers were in use for planning in the UK and I have, in the past, worked with Darrell O’Dea, Garry France and David Bordoli who have made comments on this topic.
I remember the very shaky start of the introduction of the first software packages.
I was an Activities Organiser for the CIOB South London Committee going back a good few years now, when I organised a demonstration of a software for planning (I do not remember it’s name)for the CIOB members. The evening was not a success because the computers or the software kept crashing.
The story now is very different. There are so many good packages on the market that it is a problem find the one best suited for your specific end product requirements.
During the many years in the Planning Discipline I have used many planning software packages including, P3, Suretrak, Open Plan, Powerproject and others not now heard of much.
I loved the way you could manipulate the programme data via the use of their data bases in Open Plan and P3. But and this is a big "But" I did not like the fact that you had to work on the data in the dark. By this I mean that you did not see the effect of the build up or changes as you worked. You were in fact working the mechanics to achieve the end result i.e. the Bar Chart.
In around 1984 Microplanner planning software had a version for the DOS computers and one for MAC. They were two different ways of working. The DOS way working in the Engine Room the MAC way was making use of icons and graphics. The problem was that most of the industries in this country were into using the IBM processor and therefore it did not catch on.
The advent of MS Windows opened this method of using computers and made the use of software within the grasp of every one as the old saying goes "a picture is worth more then a 1000 words". The problem in the beginning was that the computers were not able to handle the larger up front memory for the graphics. But not any more as computer power is more then capable and improving by the day.
In Powerproject you use the screen to draw the bars and logic links, or not if did not wish to. And it uses "drag and drop" to add calendars, resources, Codes, etc, etc on to the bars. It is all-graphical and yet it can do all the you could do with the "other way of working" and it does it better. I am not going to attempt list the vast capability and specification of Powerproject, but I would urge you to get yourself a demonstration copy and experience it’s power and ease of use. "
Philip,
I would like to know how you would compare Powerproject V8 with the new Open Plan and New P3e.
Regards
Daya
- 0PJPhilip Jonker ·Hi Daya,
It is simple, as real planners, P3 gives the right answers, and why do we have to switch to mickey mouse bullskit, even if we know the tools we are uding is correct. I do not personally have a share in P3, however it has the capability to do the job, and at the end of the day pay my salary. Further to this, I have given up on planning programs at the end of the job, and stil run them in the old style, brute force and temperament - 0AFAndrew Flowerdew ·All,
P3 is very reliable, powerfull but expensive and not the most user friendly software out there. Comparatively long drawn out process to put the info in but will tell you everything you ever needed to know once the info’s there. I would at this moment in time still consider P3 to be the best software available but haven’t tried out the very lastest versions.
PowerProject is very easy to use, cheap when compared to P3 but has reliability issues. (especially when calculating the money side of things) Putting info in is easy and quick and in version 8 they did improve it’s reporting capabilities greatly. Not sure what version 9 is going to bring later this year but if they have solved the reliability issues and improved the reporting further it’s then got to be considered as a real alternative to P3. It’s biggest draw back is not being able to import info from Excel. (you can export to Excel)This might change in version 9 (hopefully) as they are including the current add on .xml file import facility for MSP data transfer - but whether you will be able to use it to import spreadsheet data into an existing programmes I don’t know.
MSP 2003, has improved over previous versions and I might choose it for programming a small project but thats about it. Actually, on second thoughts, I wouldn’t even use it for that.