The pros and cons to export file from mp to pp8.

Paola VeasMember for 21 years
Created
2
3
0
Hi all,

Is it really reliable to export file from mp to asta project?

I have set up both programmes with the same characteristics, like weather and standar calendars, durations, etc.
Once I have exported a file from mp to pp, Can I assume the files are exactly the same or I should do a few changes to fix some lost information?

Cheers

Paola Veas
Assistant Planning Engineer
New Zealand - Chile

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Paola,
    MS Project does not handle project schedules the same way as Powerproject or Sciforma PS8 or Primavera P3; nor do the different versions of MSP.
    Before switching a schedule from one system to the other, you should check the options being active in both system: open Tools, Options, Schedule in MS Project, take note of the options and set up PP8 as close as possible as you have in MSP.
    I have a longer and more accurate experience in migrating projects from MSP to PS8 one way or the other, and I know a lot of reason for projects not migrating easily.
    Have a good day when you wake up in NZ.
    Alexandre
    PS Please send me a sample MSP schedule for testing
  2. 0
    Daya Sugunasingha ·
    You always have to check each item/task against the original after converting to ensure that it is correct.
    Do not just export and hope for the best or trouble awaits you.
    DS